Patterns

No heat or hot-water complaints in the last three years.

No bedbug-infested units reported in the last three years of filings.

What 311 hears from this address

43 service requests in the last three years. Most common: Noise (29) · Illegal Parking (5) · Street Condition (3) · Lost Property (2) · Street Light Condition (1) · Homeless Person Assistance (1).

Filed construction activity

$18,333,256 in permitted construction work filed since 2016 (266 filings with a declared cost) — a rough measure of how actively the owner maintains the building. Permit costs cover filed construction work only — they do not capture routine maintenance or repairs done without a permit.

What the city thinks it's worth

Tax yearCity market valueAssessed value
2025$649,469 $292,262
2026$7,954,265 $3,579,420
2027$32,833,683 $14,775,157

The city's market estimate has risen 4955% between tax years 2025 and 2027.

Building systems

Energy grade (LL33)F — did not submit required benchmarking data, posted at the entrance by law (2022 disclosure cycle)
Heating fuelNO2FUEL
Facade (Local Law 11)SWARMP — "Safe With A Repair and Maintenance Program": known facade conditions that must be repaired (cycle 9)

Restaurants in this building

RestaurantCuisineGradeNotes
Spring PlaceMediterraneanA—

Report to 311: Food poisoning · Food safety complaint

1 restaurant · 0 with mice evidence · See them on the Mice Map

Flood exposure

In the FEMA 1%-annual-chance floodplain (2015 preliminary flood maps) — lenders typically require flood insurance here.

Hurricane evacuation zone 2 of 6 — zone 1 evacuates first.

Not in the city's stormwater (cloudburst) flood maps under any modeled scenario.

6 street-flooding or sewer-backup complaints at this address since 2015 (0 in the last three years).

Sources: FEMA flood maps (coastal), NYC DEP Stormwater Flood Maps (cloudburst), NYC hurricane evacuation zones, and 311 records for this address.

Getting around

SubwayCanal St — A C E · 250 ft straight-line (about a 1-minute walk) · station accessibility: none
Canal St — 1 · 500 ft straight-line (about a 3-minute walk) · station accessibility: none
BusNearest boarding stop: 6 Av / W Broadway — M55 BxM18 · 300 ft
Citi BikeLaight St & Hudson St · 500 ft · station location as of 2026-09-23; live availability
School zones (2024–25 map)Elementary: P.S. 234 Independence School
Middle: M.S. 297. Confirm with the DOE's school search.

Distances are straight-line, not walking routes. Transit locations from the MTA and Citi Bike, bike facilities from NYC DOT, school zones from the DOE's 2024–25 maps.

Report a problem to 311

50 Varick Street

Rats or miceRats or mice
Food poisoningFood poisoning
Food safety complaintFood safety complaint
Anything elseAnything else

43 311 service requests from this address in the last three years.

311 will ask for the address, the apartment if the problem is inside, and what's wrong. Contact details are optional for most complaints; food-poisoning reports can be anonymous. Complaints appear in the city's public 311 data, usually within a day or two, and then in the Live from 311 box on this page.

Sales, deeds & mortgages

DateRecordAmountPer res. unit
2021-03-25RPTT&RET $1,500,000 — from VARICK 4 LLC; VARICK 3 LLC to 13-17 LAIGHT NY LLC $1,500,000
2021-03-25RPTT&RET $1,500,000 — from VARICK 4 LLC; VARICK 3 LLC to 13-17 LAIGHT NY LLC $1,500,000
2017-08-16Agreement $77,890,000 — from VARICK 4 LLC; VARICK 3 LLC to LADDER CAPITAL FINANCE LLC $77,890,000
2017-08-16Mortgage $26,531,106 — from VARICK 3 LLC; VARICK 4 LLC to LADDER CAPITAL FINANCE LLC $26,531,106
2017-08-16AL&R $77,890,000 — from VARICK 3 LLC; VARICK 4 LLC to LADDER CAPITAL FINANCE LLC $77,890,000
2017-08-16AL&R $77,890,000 — from VARICK 3 LLC; VARICK 4 LLC to LADDER CAPITAL FINANCE LLC $77,890,000
2017-08-16Agreement $77,890,000 — from VARICK 4 LLC; VARICK 3 LLC to LADDER CAPITAL FINANCE LLC $77,890,000
2017-08-16Deed $135,000,000 — from 50 VARICK LLC to VARICK 3 LLC; VARICK 4 LLC $135,000,000
2017-08-16Deed $135,000,000 — from 50 VARICK LLC to VARICK 3 LLC; VARICK 4 LLC $135,000,000
2017-08-16Mortgage $26,531,106 — from VARICK 3 LLC; VARICK 4 LLC to LADDER CAPITAL FINANCE LLC $26,531,106
2017-08-07Sold for $135,000,000 $135,000,000 $19,285,714
2017-01-25AL&R $500,000,000 — from 50 VARICK LLC to COLUMN FINANCIAL, INC. $500,000,000
2017-01-25AL&R $500,000,000 — from 50 VARICK LLC to COLUMN FINANCIAL, INC. $500,000,000
2017-01-12Mortgage $500,000,000 — from ARC NY24549W17, LLC; ARC NY120W5701 TRS, LLC; ARC NY333W3401, LLC; 50 VARICK LLC; ARC NY22 to COLUMN FINANCIAL, INC. $500,000,000
2017-01-12Mortgage $500,000,000 — from ARC NY24549W17, LLC; ARC NY120W5701 TRS, LLC; ARC NY333W3401, LLC; 50 VARICK LLC; ARC NY22 to COLUMN FINANCIAL, INC. $500,000,000

Ten-year activity

5002500
213
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
ConstructionEnforcementHousing & tenantsOwnership & moneyHealth & systems
Show as table
YearConstructionEnforcementHousing & tenantsOwnership & moneyHealth & systemsTotal
20171163155425213
20181251214421176
2019153171005185
2020311090656
2021351719463120
2022450180366
2023390180461
202440080654
2025440210065
2026400130356
This record is free. Keeping it free costs money.
Servers, data pipelines, weekends. Pay what you want — a dollar helps.
Chip in

The last 12 months — 64 records

DateRecord
2026-10-14Job filed: Conference in the existing studios.
2026-10-09Job filed: Conference in the existing Spring studios.
2026-10-08Job filed: Conference in the existing studios.
2026-09-23Job filed: Conference in the existing studios.
2026-09-22311: Illegal Parking — Posted Parking Sign Violation
2026-09-22Certificate of occupancy Renewal Without Change
2026-09-22Job filed: PROPOSED FACADE REPAIRS/RESTORATION PER PLANS. THERE IS NO CHANGE IN OCCUPANCY USE OR EGRESS UNDER THIS APPLICATION.
2026-09-21Job filed: Conference in the existing studios.
2026-09-21Job filed: Temporary structures for event programing at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.
2026-09-14Job filed: Fashion show in the existing studios.
2026-09-14Job filed: Temporary structures for event programing at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.
2026-09-13311: Street Condition — Cave-in
2026-09-04Job filed: Conference in the existing studios
2026-08-27Job filed: Presentation with food and beverage in the existing studios.
2026-07-29Job filed: Conference and banquet in the existing studios.
2026-07-17311: Noise - Commercial — Loud Music/Party
2026-07-17311: Noise - Residential — Loud Music/Party
2026-07-17311: Noise - Commercial — Loud Music/Party
2026-07-17311: Noise - Commercial — Loud Music/Party
2026-07-17311: Noise - Commercial — Loud Music/Party
2026-07-17311: Noise - Commercial — Loud Music/Party
2026-07-17311: Noise - Commercial — Loud Music/Party
2026-07-17Job filed: Conference in the existing banquet/exhibition hall studios.
2026-07-15311: Noise - Street/Sidewalk — Loud Music/Party
2026-07-14Permit General Construction — Signed-off
2026-07-13Job filed: Temporary structures for event programing at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.
2026-07-06Job filed: Summit in the existing banquet/exhibition hall studios.
2026-07-01Permit Mechanical Systems — Signed-off
2026-07-01Permit Mechanical Systems — Permit Issued
2026-07-01Permit Mechanical Systems — Signed-off
2026-07-01Permit Mechanical Systems — Permit Issued
2026-06-24311: Illegal Parking — Blocked Sidewalk
2026-06-24Certificate of occupancy Renewal Without Change
2026-06-02Permit General Construction — Permit Issued
2026-06-02Permit General Construction — Permit Issued
2026-06-02Permit General Construction — Permit Issued
2026-06-01Job filed: Film festival in the existing studios.
2026-06-01Job filed: Temporary structures for event programing at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.
2026-05-22Cooling tower inspection — violation AHK0
2026-05-22Cooling tower inspection — violation AHK0
2026-05-14311: Illegal Parking — Posted Parking Sign Violation
2026-05-12Restaurant inspection: SPRING PLACE — grade A
2026-05-12Job filed: Conference in the existing studios.
2026-05-11Job filed: Event with presentation and reception the existing studios.
2026-04-27Job filed: Event with presentation and dining in the existing studios.
2026-04-20Job filed: Event with presentation and dining in the existing studios.
2026-04-14Job filed: Conference in 2 floors of the existing studios.
2026-03-24Job filed: Conference with presentation and lounge in the existing Spring Studios.
2026-03-19Job filed: Conference with lecture hall and lunge.
2026-03-13Job filed: Conference with presentation, dining, exhibits and lounges.
2026-03-05311: Noise — Noise, Barking Dog (NR5)
2026-03-03Job filed: Temporary structures for event programing at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.
2026-03-02Job filed: Conference in the existing studios.
2026-02-27Certificate of occupancy Renewal Without Change
2026-02-26Job filed: Digital tech conference in the existing studios.
2026-01-13Job filed: To Obtain Certificate of Compliance for 2 existing AC condensers units at roof level as per FDNY order.
2025-12-01Job filed: Temporary structures for events at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.
2025-12-01Job filed: Exhibition and presentation.
2025-11-13Job filed: Conference in the existing studios.
2025-11-10Job filed: Conference in the existing studios.
2025-11-06Certificate of occupancy Renewal Without Change
2025-10-31Job filed: Conference events in the existing studios.
2025-10-27311: Damaged Tree — Tree Alive - in Poor Condition
2025-10-21Job filed: Conference in the existing studios.

The full timeline

2026
2026-10-14Job filed: Conference in the existing studios.
2026-10-09Job filed: Conference in the existing Spring studios.
2026-10-08Job filed: Conference in the existing studios.
2026-09-23Job filed: Conference in the existing studios.
2026-09-22311: Illegal Parking — Posted Parking Sign Violation
2026-09-22Certificate of occupancy Renewal Without Change
2026-09-22Job filed: PROPOSED FACADE REPAIRS/RESTORATION PER PLANS. THERE IS NO CHANGE IN OCCUPANCY USE OR EGRESS UNDER THIS APPLICATION.$48,000
2026-09-21Job filed: Conference in the existing studios.
2026-09-21Job filed: Temporary structures for event programing at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.$21,500
2026-09-14Job filed: Fashion show in the existing studios.
2026-09-14Job filed: Temporary structures for event programing at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.$16,500
2026-09-13311: Street Condition — Cave-in
2026-09-04Job filed: Conference in the existing studios
2026-08-27Job filed: Presentation with food and beverage in the existing studios.
2026-07-29Job filed: Conference and banquet in the existing studios.
2026-07-17311: Noise - Commercial — Loud Music/Party
2026-07-17311: Noise - Residential — Loud Music/Party
2026-07-17311: Noise - Commercial — Loud Music/Party
2026-07-17311: Noise - Commercial — Loud Music/Party
2026-07-17311: Noise - Commercial — Loud Music/Party
2026-07-17311: Noise - Commercial — Loud Music/Party
2026-07-17311: Noise - Commercial — Loud Music/Party
2026-07-17Job filed: Conference in the existing banquet/exhibition hall studios.
2026-07-15311: Noise - Street/Sidewalk — Loud Music/Party
2026-07-14Permit General Construction — Signed-off
2026-07-13Job filed: Temporary structures for event programing at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.$5,000
2026-07-06Job filed: Summit in the existing banquet/exhibition hall studios.
2026-07-01Permit Mechanical Systems — Signed-off
2026-07-01Permit Mechanical Systems — Permit Issued
2026-07-01Permit Mechanical Systems — Signed-off
2026-07-01Permit Mechanical Systems — Permit Issued
2026-06-24311: Illegal Parking — Blocked Sidewalk
2026-06-24Certificate of occupancy Renewal Without Change
2026-06-02Permit General Construction — Permit Issued
2026-06-02Permit General Construction — Permit Issued
2026-06-02Permit General Construction — Permit Issued
2026-06-01Job filed: Film festival in the existing studios.
2026-06-01Job filed: Temporary structures for event programing at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.$11,500
2026-05-22Cooling tower inspection — violation AHK0
2026-05-22Cooling tower inspection — violation AHK0
2026-05-14311: Illegal Parking — Posted Parking Sign Violation
2026-05-12Restaurant inspection: SPRING PLACE — grade A
2026-05-12Job filed: Conference in the existing studios.
2026-05-11Job filed: Event with presentation and reception the existing studios.
2026-04-27Job filed: Event with presentation and dining in the existing studios.
2026-04-20Job filed: Event with presentation and dining in the existing studios.
2026-04-14Job filed: Conference in 2 floors of the existing studios.
2026-03-24Job filed: Conference with presentation and lounge in the existing Spring Studios.
2026-03-19Job filed: Conference with lecture hall and lunge.
2026-03-13Job filed: Conference with presentation, dining, exhibits and lounges.
2026-03-05311: Noise — Noise, Barking Dog (NR5)
2026-03-03Job filed: Temporary structures for event programing at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.$6,500
2026-03-02Job filed: Conference in the existing studios.
2026-02-27Certificate of occupancy Renewal Without Change
2026-02-26Job filed: Digital tech conference in the existing studios.
2026-01-13Job filed: To Obtain Certificate of Compliance for 2 existing AC condensers units at roof level as per FDNY order.$4,000
2025
2025-12-01Job filed: Temporary structures for events at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.$22,500
2025-12-01Job filed: Exhibition and presentation.
2025-11-13Job filed: Conference in the existing studios.
2025-11-10Job filed: Conference in the existing studios.
2025-11-06Certificate of occupancy Renewal Without Change
2025-10-31Job filed: Conference events in the existing studios.
2025-10-27311: Damaged Tree — Tree Alive - in Poor Condition
2025-10-21Job filed: Conference in the existing studios.
2025-10-16Job filed: Conference in the existing studios.
2025-10-14Job filed: Conference with lectures, meeting and reception in the existing studios.
2025-10-09Job filed: Conference, with lecture hall and banquet hall in the existing studios.
2025-10-03311: Street Condition — Cave-in
2025-10-01Job filed: Conference in the existing studios.
2025-09-26Job filed: Temporary structures for events at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.$17,500
2025-09-22Job filed: Conference for a tech product launch, with lecture and exhibition.
2025-09-16Job filed: Private birthday party with dining and entertainment.
2025-09-12Job filed: Conference in various floors of the existing studios.
2025-09-10311: Street Condition — Pothole
2025-09-08Job filed: Fashion show
2025-09-03311: Sidewalk Condition — Broken Sidewalk
2025-08-18311: Noise - Street/Sidewalk — Loud Music/Party
2025-08-10311: Noise - Residential — Loud Music/Party
2025-08-08Certificate of occupancy Renewal Without Change
2025-07-12311: Noise - Residential — Loud Music/Party
2025-07-12311: Noise - Commercial — Loud Music/Party
2025-07-10Job filed: Automotive exhibition in the existing exhibition hall, studios.
2025-06-28311: Noise - Residential — Loud Music/Party
2025-06-28311: Noise - Commercial — Loud Music/Party
2025-06-28311: Noise - Commercial — Loud Music/Party
2025-06-24Job filed: Temporary structures for events at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.$12,500
2025-06-21311: Noise - Commercial — Loud Music/Party
2025-06-21311: Noise - Commercial — Banging/Pounding
2025-06-20Job filed: Tech conference for Mulesoft with presentations, demo's, food and beverage, in the existing studios.
2025-06-04311: Illegal Parking — Parking Permit Improper Use
2025-06-03Job filed: Film festival in 2 floors, with screenings, multiple seating layouts, exhibitions and lounge.
2025-05-28311: Homeless Person Assistance — Non-Chronic
2025-05-25311: Noise - Commercial — Loud Music/Party
2025-05-25311: Noise - Residential — Loud Music/Party
2025-05-25311: Noise - Commercial — Loud Music/Party
2025-05-24311: Noise - Commercial — Loud Music/Party
2025-05-24311: Noise - Residential — Loud Music/Party
2025-05-24311: Noise - Residential — Loud Music/Party
2025-05-19Job filed: Conference with meeting rooms, lounge and dining room at the existing Spring Studios.
2025-05-14Job filed: Conference with meeting rooms, lounge and dining room at the existing Spring Studios.
2025-05-12Certificate of occupancy Renewal Without Change
2025-05-12Job filed: Conference with lectures, meetings and areas for food and beverage.
2025-04-23Job filed: Conference with lectures and reception on the existing studios.
2025-04-23Job filed: Four day Art Fair on floors 1, 5, 6, 7 for ticketed guests only.
2025-04-17Job filed: Conference with lectures and reception with food and beverage.
2025-04-07Job filed: Film screening, in the existing studios, with dining, food, beverage and entertainment.
2025-04-03Permit Mechanical Systems — Signed-off
2025-03-31Permit General Construction — Permit Issued
2025-03-31Permit General Construction — Permit Issued
2025-03-31Permit General Construction — Permit Issued
2025-03-29Job filed: REPLACE WATER COOLED AIR CONDITIONER UNIT AS PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS$152,350
2025-03-28Job filed: Conference with lectures, dining, and lounges.
2025-03-25Job filed: Summit for Goldman Sachs with lectures, lounges and dining.
2025-03-20Job filed: Temporary structures for event programing at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.$21,500
2025-03-14Job filed: Conference with lectures and areas with food and beverage.
2025-02-27Permit General Construction — Signed-off
2025-02-25Permit General Construction — Permit Issued
2025-02-19Job filed: Temporary structures for events at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.$22,500
2025-02-19Job filed: Conference, in two floors, existing studios, with seated presentation, lounge and exhibition hall.
2025-02-14Certificate of occupancy Renewal Without Change
2025-01-21Job filed: Fashion exhibition hall and trade show.
2024
2024-12-20Restaurant inspection: SPRING PLACE — grade A
2024-12-14311: Lost Property — Bag/Wallet
2024-12-12Permit General Construction — Signed-off
2024-12-06Job filed: Temporary structures for a Hangar 4 event at Spring Studios. Removed at the end of the programing. No changes to existing structures, use or egress.$5,000
2024-12-05Job filed: Conference with lectures and lounge.
2024-12-03Cooling tower inspection
2024-11-19Job filed: Summit with meetings and lounge.
2024-11-13Job filed: Conference with lectures, exhibits, food and beverage.
2024-11-12Job filed: Corporate summit, with lectures and dining in the existing studios.
2024-11-10311: Noise - Commercial — Loud Music/Party
2024-11-07Certificate of occupancy Renewal Without Change
2024-10-22Restaurant inspection: SPRING PLACE
2024-10-17Job filed: Conference with lectures and reception.
2024-10-15Air permit (REGISTRATION), fuel: NO2FUEL
2024-10-09Job filed: Conference with lecture halls and lounge
2024-09-20Asbestos abatement: Removal — JVN Restoration Inc.
2024-09-09Permit Mechanical Systems — Signed-off
2024-09-09Permit General Construction — Signed-off
2024-09-06311: Lost Property — Bag/Wallet
2024-09-03Job filed: Fashion show
2024-08-23Permit General Construction — Signed-off
2024-07-25Job filed: Event with food, beverage, and recreational activities in 2 floors, existing studios.
2024-07-12Job filed: General Construction work & protection related to Mechanical Systems Upgrades.$500,000
2024-07-10Job filed: Fashion exhibition hall and trade show.
2024-07-03Job filed: INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$1,000
2024-06-24Job filed: Conference, with presentations, exhibits and lounges with food and beverage.
2024-06-17Job filed: 2 events simultaneous in the studios, one for Future 50 6th floor, and the other for Stanley, 5th floor. With lectures, exhibits and lounges.
2024-06-12311: Illegal Parking — Blocked Sidewalk
2024-06-04Job filed: INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$1,000
2024-06-04Job filed: INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$1,000
2024-06-04Permit Supported Scaffold — Signed-off
2024-06-04Permit Sidewalk Shed — Signed-off
2024-06-03Certificate of occupancy Renewal Without Change
2024-05-31Job filed: Film festival in 2 floors, with screenings, multiple seating layouts, exhibitions and lounge.
2024-05-26311: Noise - Commercial — Loud Music/Party
2024-05-22Permit Mechanical Systems — Signed-off
2024-05-16Job filed: Event with exhibition hall, presentation areas and lounge.
2024-05-15Job filed: Mechanical work related to LL87 upgrades$1,786,265
2024-05-13Job filed: Conference with meetings, presentations and receptions.
2024-04-26Job filed: Summit with lecture hall and a reception with food and beverage.
2024-04-17Job filed: Make up launch with presentations, displays, food and beverage.
2024-04-11Permit General Construction — Permit Issued
2024-04-05Job filed: Conference with areas with food and beverage.
2024-03-28Job filed: Installation of temporary partitions, no alt to exist structures for Annual Independent Art Fair. A TPA permit is required. Producer is responsible to$6,000
2024-03-26Job filed: Art Fair for ticketed guests only (retail)
2024-03-08Certificate of occupancy Renewal Without Change
2024-02-27Job filed: Eyeglasses fashion exhibition with accessory cafe.
2024-02-23311: Noise - Street/Sidewalk — Loud Music/Party
2024-02-23311: Noise - Commercial — Loud Music/Party
2024-02-16Permit Sprinklers — Signed-off
2024-02-10311: Noise - Commercial — Loud Music/Party
2024-01-29Facade (LL11) filing, cycle 9: SWARMP
2024-01-12Job filed: Fashion exhibition
2024-01-03Permit General Construction — Signed-off
2023
2023-12-27Job filed: Activities with food and beverage and entertainment.
2023-12-22Job filed: Temporary structures for a DS event in the studios. Removed at the end of the programing. No changes to existing structures, use or egress.$7,000
2023-12-21311: Street Light Condition — Street Light Out
2023-12-14Certificate of occupancy Renewal Without Change
2023-12-01Job filed: Presentations, lectures and exhibition hall, with food and beverage.
2023-11-14Cooling tower inspection
2023-11-13Job filed: Conference with food and beverage.
2023-11-08Job filed: Presentation with food and beverage.
2023-11-03Cooling tower inspection
2023-11-03Cooling tower inspection
2023-11-03Job filed: Event with awards presentation food, beverage and entertainment.
2023-10-26Job filed: Gala with food and beverage.
2023-10-20Job filed: Conference with meetings, presentation and dining.
2023-10-04311: Illegal Parking — Posted Parking Sign Violation
2023-09-25Job filed: Summit with presentations, exhibits and receptions.
2023-09-21Certificate of occupancy Renewal Without Change
2023-09-21Job filed: Seated presentation
2023-09-20Job filed: Wedding, with ceremony, reception, dinner and party, with food, beverage and entertainment.
2023-09-18Job filed: Conference with presentation and meeting areas.
2023-09-17311: Noise - Commercial — Banging/Pounding
2023-09-17311: Noise - Street/Sidewalk — Loud Music/Party
2023-09-17311: Noise - Commercial — Loud Music/Party
2023-09-17311: Noise - Commercial — Loud Music/Party
2023-09-17311: Noise - Commercial — Loud Music/Party
2023-08-29Job filed: Fashion week hub with fashion shows programming, various layout alternates and accessory spaces.
2023-08-16Job filed: Medical conference with seated presentation and demonstrations.
2023-08-16Permit General Construction — Signed-off
2023-08-02Permit General Construction — Signed-off
2023-08-01Job filed: Car display event, with presentation, exhibition and lounge.
2023-07-31Job filed: Temporary structures for a GMC event. Removed at the end of the programing. No changes to existing structures, use or egress.$10,000
2023-07-13Job filed: Fashion exhibition hall
2023-06-20Job filed: Conference with presentation and dining areas.
2023-06-07Job filed: Film festival, multiple layouts, an exhibition hall and receptions.
2023-06-03311: Noise - Commercial — Loud Music/Party
2023-06-03311: Noise - Commercial — Loud Music/Party
2023-06-03311: Noise - Commercial — Loud Music/Party
2023-05-26Restaurant inspection: SPRING PLACE — grade A
2023-05-23Job filed: Exhibition hall with areas for lectures and food and beverage.
2023-05-16Job filed: Temporary structures for events at Spring Studios. Structures removed at the end of the programing. No changes to existing structures, use or egress$19,000
2023-05-09Job filed: Meeting with food and beverage.
2023-04-29311: Noise - Commercial — Loud Music/Party
2023-04-29311: Noise - Commercial — Loud Music/Party
2023-04-28Job filed: Exhibitions, presentations and areas for food and beverage.
2023-04-25Job filed: Art Fair for ticketed guests only (retail)
2023-04-22311: Noise - Street/Sidewalk — Loud Music/Party
2023-04-22311: Noise - Commercial — Loud Music/Party
2023-04-17Job filed: Conference, with area for presentations, lounge and dining.
2023-04-07311: Illegal Parking — Blocked Sidewalk
2023-04-06Job filed: Temporary platform for Spring Studios events. Structures removed at the end of the programing. No changes to existing structures, use or egress.$19,000
2023-04-05Job filed: Conference with food and beverage.
2023-04-05Job filed: Event program with a conference, lounge and dining.
2023-03-30Job filed: Presentations with lounge and dining area.
2023-03-17311: Street Sign - Dangling — One Way
2023-03-16Job filed: Presentations, conference and lounge with food and beverage.
2023-03-10311: Noise - Commercial — Loud Music/Party
2023-03-10311: Noise - Commercial — Loud Music/Party
2023-03-08Job filed: Eye wear exhibition, trade show, with accessory cafe area.
2023-03-06Job filed: Temporary platform for Spring Studios events. Structures removed at the end of the programing. No changes to existing structures, use or egress.$12,000
2023-03-03Job filed: Presentation with seated audience, with accessory lounge and dining.
2023-02-03Job filed: Fashion show series with multiple layouts and support spaces.
2023-01-19Job filed: Fashion exhibition hall and cafe lounge.
2022
2022-11-15311: Encampment — N/A
2022-11-13Job filed: Conference, with presentations, exhibits, food and beverage.
2022-11-07Job filed: Corporate summit with presentations on the 6th floor and receptions with food and beverage on the 5th floor.
2022-11-04Permit General Construction — Signed-off
2022-11-02Job filed: Conference, with presentation's, displays, meeting rooms and dining. Various spaces and alternate layouts with uses F1b, F3 and F4.
2022-11-02Job filed: Temporary structures for the SLB event. Removed at the end of the programing. No changes to existing structures, use or egress. SAPO# 676913$10,000
2022-10-27Certificate of occupancy Renewal Without Change
2022-10-18Job filed: Presentations, and areas for meeting, food and beverage.
2022-10-14Job filed: Convention, with presentations and reception, with food and beverage.
2022-10-11Job filed: Conference, with presentations and dining.
2022-10-08311: Noise - Residential — Loud Music/Party
2022-10-08311: Noise - Residential — Loud Music/Party
2022-10-05Job filed: Conference with seated presentations, work areas and dining.
2022-10-03Job filed: Family event, with ceremony, food, beverage and entertainment.
2022-09-06Job filed: New York Fashion Week, programming with various fashion shows, layouts and associated spaces.
2022-09-01Cooling tower inspection
2022-09-01Cooling tower inspection
2022-08-31Job filed: Tennis themed event, with seated audience and lounges for the viewing of the US Open broadcasting on a screen.
2022-08-22Job filed: New York Fashion Week, programming with various fashion shows, layouts and associated spaces.
2022-08-19Job filed: Temporary structures for NYFW at Spring Structures removed at the end of the programing. No changes to existing structures, use or egress.$15,000
2022-08-18Job filed: Tennis themed event, with seated audience and lounges for the viewing of the US Open broadcasting on a screen.
2022-08-10311: Illegal Parking — Posted Parking Sign Violation
2022-08-08Permit General Construction — Signed-off
2022-08-05Permit General Construction — Signed-off
2022-08-01Certificate of occupancy Renewal Without Change
2022-08-01Job filed: Temporary platform for Spring Studios events. Structures removed at the end of the programing. No changes to existing structures, use or egress.$7,000
2022-07-31Job filed: Wedding ceremony and reception, with food and beverage,
2022-07-28311: Noise - Commercial — Loud Music/Party
2022-07-28311: Noise - Residential — Loud Music/Party
2022-07-23Job filed: Fashion exhibitor show room
2022-07-13Job filed: Fashion trade show, exhibition hall.
2022-07-03Job filed: Fashion trade show, exhibition hall.
2022-06-28311: Illegal Parking — Posted Parking Sign Violation
2022-06-27Job filed: Conference with 2 layouts.
2022-06-25311: Noise - Commercial — Loud Music/Party
2022-06-20Job filed: Exhibition hall and presentations of brands and products.
2022-06-19Job filed: Presentations and and panel discussions, with food and beverage.
2022-06-16311: Illegal Parking — Blocked Sidewalk
2022-06-07Job filed: Event series, with film screenings, presentations, exhibitions and receptions.
2022-05-24Job filed: Reception, with food, beverage and entertainment.
2022-05-20Job filed: 2 Day conference with receptions.
2022-05-19Job filed: Wedding, with ceremony and reception, with food, beverage and entertainment.
2022-05-17Elevator permit: REGROOVE TRACTION SHEAVE AND REPLACE HOIST CABLES.ALL WORK TO COMPLY WITH ASME/ANSI A 17.1 2000/2003, CHAPTER 30, APPENDIX K.ALL T$9,500
2022-05-14311: Street Condition — Defective Hardware
2022-05-13Job filed: Exhibition, presentation and lounges
2022-05-02Certificate of occupancy Renewal Without Change
2022-04-22Job filed: Art fair in multiple floors
2022-04-20311: Illegal Parking — Posted Parking Sign Violation
2022-04-19Job filed: Conference and reception
2022-04-13Job filed: Corporate conference and receptions
2022-04-01Job filed: Conference and reception
2022-03-31Job filed: Temporary platform for Spring Studios events. Structures removed at the end of the programing. No changes to existing structures, use or egress.$7,000
2022-03-31Permit General Construction — Signed-off
2022-03-29Job filed: Temporary structures for Richard Attias event Removed at the end of the programing. No changes to existing structures, use or egress.$10,000
2022-03-29Job filed: Conference, exhibition and reception
2022-03-23311: Homeless Person Assistance
2022-03-22311: Homeless Person Assistance
2022-03-19311: Homeless Person Assistance
2022-03-18311: Homeless Person Assistance
2022-03-08Job filed: Eyewear exhibitor showcase
2022-02-28311: Illegal Parking — Blocked Bike Lane
2022-02-21311: Vaccine Mandate Non-Compliance — Customer Proof of Vaccination Not Checked
2022-02-03Certificate of occupancy Renewal Without Change
2022-01-28Job filed: Fashion show series part of New York Fashion Week
2022-01-20Job filed: Temporary structures for NYFW at Spring Structures removed at the end of the programing. No changes to existing structures, use or egress.$10,000
2022-01-03311: Vaccine Mandate Non-Compliance — Employee Proof of Vaccination Not Checked
2021
2021-12-28311: Vaccine Mandate Non-Compliance — Employee Proof of Vaccination Not Checked
2021-12-22DOB violation AEUHAZ1: FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
2021-12-16Job filed: INSTALLATION OF SIDEWALK SHED FOR PEDESTRIAN SAFETY DURING CONSTRUCTION. SIDEWALK SHED SHALL COMPLY WITH NYCC 2014 CHAPTER 33 . NO CHANGE IN EGRESS, U$1,000
2021-12-16Permit Sidewalk Shed — Signed-off
2021-12-07311: Vaccine Mandate Non-Compliance — Employee Proof of Vaccination Not Checked
2021-11-24DOB violation AEUHAZ1: FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
2021-11-17311: Vaccine Mandate Non-Compliance — Customer Proof of Vaccination Not Checked
2021-11-09Permit General Construction — Signed-off
2021-11-06311: Vaccine Mandate Non-Compliance — Employee Proof of Vaccination Not Checked
2021-11-04311: Noise - Street/Sidewalk — Loud Music/Party
2021-11-04311: Noise - Commercial — Loud Music/Party
2021-11-03Job filed: Temporary scenic props for MCW event at Spring Studios Removed at the end of the programing. No changes to existing structures, use or egress.$5,000
2021-11-01Certificate of occupancy Renewal Without Change
2021-10-27311: Vaccine Mandate Non-Compliance — Employee Proof of Vaccination Not Checked
2021-10-20Job filed: Temporary platform for Spring Studios events. Structures removed at the end of the programing. No changes to existing structures, use or egress.$7,000
2021-10-18Job filed: Exposition with conference, food, beverage and entertainment.
2021-10-15ECB CLASS - 2 violation: FAILURE TO MAINTAIN BLDG EXTERIOR WALLS/FACADE&APPURTENANCES.@W ELEVATION,EXP1 OBSERVED:VERT CRACKS,DAMAGED MORTAR JOINTS&MISSING $625
2021-10-13DOB violation AEUHAZ1: FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
2021-10-13DOB violation AEUHAZ1: FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
2021-10-10311: Vaccine Mandate Non-Compliance — Customer Proof of Vaccination Not Checked
2021-10-07311: Lost Property — Electronics/Phones
2021-10-06Job filed: Temporary platform for Spring Studios events. Structures removed at the end of the programing. No changes to existing structures, use or egress.$5,000
2021-10-06Job filed: Conference, with presentations, exhibits, food and beverage.
2021-09-23Permit Boiler Equipment — Signed-off
2021-09-22311: Noise — Noise: Alarms (NR3)
2021-09-14ECB CLASS - 1 violation: FAILURE TO TAKE&PROVIDE ADEQUATE SAFETY MEASURE SWS@ADJ BLDG N&S OF EXP1W ELEVATION 50VARICKST.NOTE ATOI SHED DIDNT EXTEND TO S&WA
2021-09-08Cooling tower inspection
2021-09-08Cooling tower inspection
2021-09-08Job filed: Fashion for invited guests only, part of NY Fashion Week
2021-09-03ECB CLASS - 1 violation: FAILURE TO MAINTAIN BUILDING EXTERIOR WALLS/FACADE AND APPURTENANCES:NOTE:AT TIME OF INSPECTION VIEW AT EXP #1 WEST ELEVATION CRAC$2,500
2021-09-03ECB CLASS - 1 violation: FAILURE TO COMPLY WITH ORDER OF COMMISSIONER.NOTE:AT PRESENT TIME NO ACCEPTABLE STRUCTURAL STABILITY EVALUATION REPORT OF BUILDING
2021-09-01DOB violation AEUHAZ1: FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
2021-09-01Job filed: Fashion show series per of NY Fashion Week.
2021-08-31Job filed: Fashion show series part of NY Fashion Week
2021-08-25311: Hazardous Materials — Chemical Odor (HD1)
2021-08-25311: Street Condition — Blocked - Construction
2021-08-22Permit General Construction — Signed-off
2021-08-17Job filed: Temporary structures for NYFW at Spring Structures removed at the end of the programing. No changes to existing structures, use or egress.$15,000
2021-08-11Certificate of occupancy Renewal Without Change
2021-08-09Permit General Construction — Signed-off
2021-08-09Permit General Construction — Signed-off
2021-08-09Permit General Construction — Signed-off
2021-08-05Permit PL — ISSUED
2021-07-26Job filed: Fashion exhibitor showcase
2021-07-21ECB CLASS - 1 violation: FAILURE TO PROVIDE SIDEWALK SHED WHERE REQUIRED.NOTE:AT TIME OF INSPECTION OBSERVED AT EXP #1 WEST ELEVATION MISSING BRICKS AT FLO
2021-07-21ECB CLASS - 1 violation: FAILURE TO MAINTAIN BUILDING WALLS AND APPURTENANCES.NOTES:AT TIME OF INSPECTION OBSERVED DAMAGED/CRACKED MORTAR JOINTS AND MISSIN$2,500
2021-07-13Permit General Construction — Signed-off
2021-07-10ECB CLASS - 2 violation: FAILURE TO MAINTAIN BUILDING EXTERIOR WALLS/FACADE AND APPURTENANCES:NOTE:AT TIME OF INSPECTION VIEW AT EXP #1 DAMAGED JOINTS AND $1,250
2021-07-08Job filed: Ballet festival with seated audience
2021-07-08Job filed: Temporary structures for events at Spring Studios. Structures removed at the end of the programing. No changes to existing structures, use or egress$19,000
2021-06-21Permit General Construction — Signed-off
2021-06-19Job filed: HBO events for premiere of TV series
2021-06-18Job filed: Temporary structures and occupancy for HBO Event Removed at the end of the programing. No changes to existing structures, use or egress. SAPO Event I$35,000
2021-06-10311: Illegal Parking — Parking Permit Improper Use
2021-06-10311: Illegal Parking — Blocked Sidewalk
2021-06-10311: Illegal Parking — Blocked Sidewalk
2021-06-08Job filed: Temporary structures for Tribeca Film Fest programing. Structures removed at the end of the programing. No changes to existing structures, use or egr$25,000
2021-06-06Permit General Construction — Signed-off
2021-06-02ECB CLASS - 1 violation: OWNER FAILED TO REPAIR DEFECTIVE CONDITIONS (EXP #1 WEST E.)MISSING BRICKS AT 1ST AND 2ND AND 5TH AND 7TH FLOORS/EXP #3, EAST ELEV
2021-06-02Job filed: Programming for Tribeca Film Fest, in existing studios on the 5 and 6 floors and roof.
2021-06-01Job filed: Temporary structures for Tribeca Film Fest programing. Structures removed at the end of the programing. No changes to existing structures, use or egr$25,000
2021-05-28Permit Sprinklers — Signed-off
2021-05-11311: Sewer — Catch Basin Clogged/Flooding (Use Comments) (SC)
2021-05-05311: Elevator — Elevator - Multiple Devices On Property
2021-05-05ECB CLASS - 1 violation: OUT OF SEERVICE$1,250
2021-05-05DOB complaint, category ?
2021-04-29DOB violation EGRADE: FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3
2021-04-27Job filed: Infill existing opening and install double fire rated doors at 1st floor space.$5,000
2021-04-15Permit General Construction — Signed-off
2021-04-08Job filed: Infill existing opening and install double fire rated doors at 1st floor space.$5,000
2021-04-06EASE — from VARICK 3 LLC; VARICK 3 LLC; VARICK 4 LLC; VARICK 4 LLC to 13-17 LAIGHT NY LLC; 13-17 LAIGHT NY LLC
2021-04-06EASE — from VARICK 3 LLC; VARICK 3 LLC; VARICK 4 LLC; VARICK 4 LLC to 13-17 LAIGHT NY LLC; 13-17 LAIGHT NY LLC
2021-04-06EASE — from VARICK 3 LLC; VARICK 3 LLC; VARICK 4 LLC; VARICK 4 LLC to 13-17 LAIGHT NY LLC; 13-17 LAIGHT NY LLC
2021-04-06EASE — from VARICK 3 LLC; VARICK 3 LLC; VARICK 4 LLC; VARICK 4 LLC to 13-17 LAIGHT NY LLC; 13-17 LAIGHT NY LLC
2021-04-06EASE — from VARICK 3 LLC; VARICK 3 LLC; VARICK 4 LLC; VARICK 4 LLC to 13-17 LAIGHT NY LLC; 13-17 LAIGHT NY LLC
2021-04-06EASE — from VARICK 3 LLC; VARICK 3 LLC; VARICK 4 LLC; VARICK 4 LLC to 13-17 LAIGHT NY LLC; 13-17 LAIGHT NY LLC
2021-04-06EASE — from VARICK 3 LLC; VARICK 3 LLC; VARICK 4 LLC; VARICK 4 LLC to 13-17 LAIGHT NY LLC; 13-17 LAIGHT NY LLC
2021-04-06EASE — from VARICK 3 LLC; VARICK 3 LLC; VARICK 4 LLC; VARICK 4 LLC to 13-17 LAIGHT NY LLC; 13-17 LAIGHT NY LLC
2021-04-06EASE — from VARICK 3 LLC; VARICK 3 LLC; VARICK 4 LLC; VARICK 4 LLC to 13-17 LAIGHT NY LLC; 13-17 LAIGHT NY LLC
2021-03-30ECB CLASS - 2 violation: 27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED $500
2021-03-25CERT — from CHICAGO TITLE INSURANCE COMPANY
2021-03-25SMIS — from PARAMOUNT GROUP FUND VIII 15 LAIGHT LP
2021-03-25ZONE — from 13-17 LAIGHT NY LLC
2021-03-25SMIS — from WELLS FARGO BANK, NATIONAL ASSOCIATION
2021-03-25SMIS — from PARAMOUNT GROUP FUND VIII 15 LAIGHT LP
2021-03-25SMIS — from VARICK 4 LLC; VERIZON NEW YORK INC.; VARICK 3 LLC; 13-17 LAIGHT NY LLC
2021-03-25ZONE — from 13-17 LAIGHT NY LLC
2021-03-25CERT — from CHICAGO TITLE INSURANCE COMPANY
2021-03-25ZONE — from 13-17 LAIGHT NY LLC
2021-03-25CERT — from CHICAGO TITLE INSURANCE COMPANY
2021-03-25ZONE — from 13-17 LAIGHT NY LLC
2021-03-25SMIS — from VARICK 4 LLC; VERIZON NEW YORK INC.; VARICK 3 LLC; 13-17 LAIGHT NY LLC
2021-03-25SMIS — from PARAMOUNT GROUP FUND VIII 15 LAIGHT LP
2021-03-25SMIS — from WELLS FARGO BANK, NATIONAL ASSOCIATION
2021-03-25CERT — from CHICAGO TITLE INSURANCE COMPANY
2021-03-25SMIS — from WELLS FARGO BANK, NATIONAL ASSOCIATION
2021-03-25SMIS — from WELLS FARGO BANK, NATIONAL ASSOCIATION
2021-03-25SMIS — from VARICK 4 LLC; VERIZON NEW YORK INC.; VARICK 3 LLC; 13-17 LAIGHT NY LLC
2021-03-25RPTT&RET $1,500,000 — from VARICK 4 LLC; VARICK 3 LLC to 13-17 LAIGHT NY LLC$1,500,000
2021-03-25CERT — from CHICAGO TITLE INSURANCE COMPANY
2021-03-25SMIS — from PARAMOUNT GROUP FUND VIII 15 LAIGHT LP
2021-03-25RPTT&RET $1,500,000 — from VARICK 4 LLC; VARICK 3 LLC to 13-17 LAIGHT NY LLC$1,500,000
2021-03-25CERT — from CHICAGO TITLE INSURANCE COMPANY
2021-03-25SMIS — from WELLS FARGO BANK, NATIONAL ASSOCIATION
2021-03-25SMIS — from PARAMOUNT GROUP FUND VIII 15 LAIGHT LP
2021-03-25SMIS — from VARICK 4 LLC; VERIZON NEW YORK INC.; VARICK 3 LLC; 13-17 LAIGHT NY LLC
2021-03-25ZONE — from 13-17 LAIGHT NY LLC
2021-03-25SMIS — from PARAMOUNT GROUP FUND VIII 15 LAIGHT LP
2021-03-25SMIS — from VARICK 4 LLC; VERIZON NEW YORK INC.; VARICK 3 LLC; 13-17 LAIGHT NY LLC
2021-03-25ZONE — from 13-17 LAIGHT NY LLC
2021-03-25ZONE — from 13-17 LAIGHT NY LLC
2021-03-25SMIS — from VARICK 4 LLC; VERIZON NEW YORK INC.; VARICK 3 LLC; 13-17 LAIGHT NY LLC
2021-03-25SMIS — from PARAMOUNT GROUP FUND VIII 15 LAIGHT LP
2021-03-25CERT — from CHICAGO TITLE INSURANCE COMPANY
2021-03-25SMIS — from WELLS FARGO BANK, NATIONAL ASSOCIATION
2021-03-25SMIS — from VARICK 4 LLC; VERIZON NEW YORK INC.; VARICK 3 LLC; 13-17 LAIGHT NY LLC
2021-03-25SMIS — from WELLS FARGO BANK, NATIONAL ASSOCIATION
2021-02-20311: Noise - Helicopter — Other
2021-02-03Elevator permit: NOUVEAU IS TAKING OF EBN 1724/13 TO HAVE IT TESTED AND SIGNED OFF- WORK DONE BY OTHERS: FURNISH AN DINSTALL 1 1/2 HOUR TEST HOLLOW$16,000
2021-01-10311: Noise - Helicopter — Other
2020
2020-12-18Permit Mechanical Systems — Signed-off
2020-11-06311: Noise - Street/Sidewalk — Loud Music/Party
2020-11-02DOB violation BENCH: FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4
2020-10-06Permit Mechanical Systems — Signed-off
2020-09-29ECB CLASS - 2 violation: 27-929.1 A.C.27-929.1,FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REP$1,250
2020-09-26311: NonCompliance with Phased Reopening — Business not in compliance
2020-09-18Permit Sprinklers — Signed-off
2020-09-10Job filed: Modification of existing Sprinkler System.$20,000
2020-08-24Asbestos abatement: Removal — JVN Restoration Inc.
2020-08-24Asbestos abatement: Removal — JVN Restoration Inc.
2020-08-24Asbestos abatement: Removal — JVN Restoration Inc.
2020-08-19Job filed: Plumbing work related to Chiller and BMS intergration project.$195,000
2020-08-18Elevator permit: -Modification to the existing controller to install Door Position Monitoring System (DPM) as per requirements of ASME A17.3 of 200$32,000
2020-08-10Certificate of occupancy Temporary
2020-08-02DOB violation BENCH: FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4
2020-07-15311: NonCompliance with Phased Reopening — Business not in compliance
2020-07-13311: Street Condition — Pothole
2020-07-08311: NonCompliance with Phased Reopening — Business not in compliance
2020-05-11Certificate of occupancy Temporary
2020-05-02DOB violation BENCH: FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4
2020-03-20DOB violation E:
2020-03-20DOB violation E:
2020-03-20DOB violation E:
2020-03-20DOB violation E:
2020-03-20DOB violation E:
2020-03-20DOB violation E:
2020-03-14311: Missed Collection (All Materials) — 2 Bulk-Missed Collection
2020-03-12311: Request Large Bulky Item Collection — Request Large Bulky Item Collection
2020-03-11Job filed: Install an Outdoor Emergency Generator at Roof Level$35,000
2020-03-11Job filed: Install an Outdoor Emergency Generator with Fuel Oil Storage at Roof Level.$12,000
2020-03-06311: Request Large Bulky Item Collection — Request Large Bulky Item Collection
2020-03-02Elevator permit: Modification to the existing controller to install Door Position Monitoring System (DPM) as per requirements of ASME A17.3 of 2002$64,000
2020-02-13Job filed: 20_071- Art fair with cocktails for ticketed or invited guests only. With food and beverage.
2020-02-13Job filed: INSTALL OF TEMP SCENIC WALLS, ELEMENTS, AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES, FOR IAF. TPA PERMIT IS REQUIRED. PRODUCER IS RES$5,000
2020-02-13Job filed: INSTALL OF TEMP SCENIC WALLS, ELEMENTS, AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES, FOR IAF. TPA PERMIT IS REQUIRED. PRODUCER IS RES$5,000
2020-02-13Job filed: INSTALL OF TEMP SCENIC WALLS, ELEMENTS, AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES, FOR IAF. TPA PERMIT IS REQUIRED. PRODUCER IS RES$5,000
2020-02-13Permit AL — ISSUED
2020-02-10Job filed: 20_094 - Summit with conference and cocktails with food and beverage for Similarweb. Invited guests only.
2020-02-06Certificate of occupancy Temporary
2020-02-06Job filed: INSTALL OF TEMP PLATFORMS AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES, FOR SIMILARWEB. TPA PERMIT IS REQUIRED. PRODUCER IS RESPONSIBL$5,000
2020-02-06Job filed: INSTALL OF TEMP PLATFORMS AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES, FOR SIMILARWEB. TPA PERMIT IS REQUIRED. PRODUCER IS RESPONSIBL$5,000
2020-02-06Permit AL — ISSUED
2020-02-03Asbestos abatement: Removal — PAR Environmental Corporation
2020-01-27Job filed: 20_007-Fashion show series, main hub for New York's Fashion Week, for invited guests. Various layouts on 5th & 6th floors. 5th and 6th Floors are not
2020-01-23Job filed: 20_033- CONFERENCE WITH FOOD AND BEVERAGE. FOR TICKETED OR INVITED GUESTS ONLY. TWO LAYOUTS ON THE FIFTH FLOOR.
2020-01-22Job filed: INSTALL OF TEMP PLATFORMS, TRUSSES, SCENIC ELEMENTS, AND PRODUCTION EQUIPMENT, NO ALTERATIONS TO EXIST STRUCTURES,FOR ACCELERATION TEAM MEETING. TPA P$5,000
2020-01-22Job filed: INSTALL OF TEMP PLATFORMS, TRUSSES, SCENIC ELEMENTS, AND PRODUCTION EQUIPMENT, NO ALTERATIONS TO EXIST STRUCTURES,FOR ACCELERATION TEAM MEETING. TPA P$5,000
2020-01-22Job filed: INSTALL OF TEMP PLATFORMS, TRUSSES, SCENIC ELEMENTS, AND PRODUCTION EQUIPMENT, NO ALTERATIONS TO EXIST STRUCTURES,FOR ACCELERATION TEAM MEETING. TPA P$5,000
2020-01-22Permit AL — ISSUED
2020-01-16Job filed: INSTALL OF TEMP TENT, PLATFORMS, AND SCENIC ELEMENTS FOR NYFW THE SHOWS, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. SAPO PERMIT 5$5,000
2020-01-16Job filed: INSTALL OF TEMP TENT, PLATFORMS, AND SCENIC ELEMENTS FOR NYFW THE SHOWS, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. SAPO PERMIT 5$5,000
2020-01-16Permit AL — ISSUED
2020-01-13Job filed: Modification of existing sprinkler system for office layout renovation at part of 7th floor.$6,000
2020-01-13Job filed: Install new HVAC system in part of existing office space at 7th floor$32,000
2020-01-08311: Sanitation Condition — 15 Street Cond/Dump-Out/Drop-Off
2020-01-06Job filed: AFA 20_ 032- Fashion trade show for Men's clothing. For invited guests only.
2019
2019-12-09Job filed: 19_983-Deerfield Holiday Party - 2 part event with food and beverage for invited guests only.
2019-12-05Job filed: FILING FOR GENERAL CONSTRUCTION RELATED TO THE CHILLER REPLACEMENT AND BMS INTEGRATION AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS O$950,000
2019-12-05Job filed: FILING FOR GENERAL CONSTRUCTION RELATED TO THE CHILLER REPLACEMENT AND BMS INTEGRATION AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS O$950,000
2019-12-04Permit AL — ISSUED
2019-12-03Job filed: 19_990-Popup bar & restaurants for Priceless with food and beverage. Open to public, monitored occupancy. 5 pm to 12:30 am (each day)
2019-12-03Job filed: INSTALL OF TEMP PLATFORMS, TRUSSES, SCENIC ELEMENTS, AND PRODUCTION EQUIPMENT, NO ALTERATIONS TO EXIST STRUCTURES, FOR BEYOND FOOD PRICELESS. TPA PERM$5,000
2019-11-25Job filed: 19_978-Lobel Wedding
2019-11-25Job filed: INSTALL OF TEMP PLATFORMS, TRUSSES, SCENIC STRUCTURES, AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES, FOR THE LOBEL WEDDING. TPA PERMIT $5,000
2019-11-25Job filed: INSTALL OF TEMP PLATFORMS, TRUSSES, SCENIC STRUCTURES, AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES, FOR THE LOBEL WEDDING. TPA PERMIT $5,000
2019-11-25Permit AL — ISSUED
2019-11-12DOB violation LL2604S: FAILED TO FILE FINAL SPRINKLER REPORT BY JULY 1, 2019
2019-11-12Job filed: 19_947-IBM Security Tech Conference with food and beverage, for ticketed persons only. Event setup ready by 11/20, 5am.
2019-11-12Job filed: INSTALL OF TEMP PLATFORMS, AND PRODUCTION EQUIPMENT, NO ALTERATIONS TO EXIST STRUCTURES, FOR IBM SECURITY. TPA PERMIT IS REQUIRED.PRODUCER IS RESPONSI$5,000
2019-11-12Permit AL — ISSUED
2019-11-11Job filed: a marketing conference with food and beverage
2019-11-08Job filed: a non-profit gala for invited guests only, with food and beverage
2019-11-07Job filed: 19_939-Tech conference for Medidata with food and beverage, for invited guests only. Non - Simultaneous Use of Floors 800 persons max in all TPA area
2019-11-07Job filed: Mechanical work related to chiller replacement and BMS intergration.$2,000,000
2019-11-07Permit Mechanical Systems — Signed-off
2019-11-06311: Noise - Vehicle — Engine Idling
2019-11-06Job filed: INSTALL OF TEMP PLATFORMS, SCENIC ELEMENTS, AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES, TPA PERMIT IS REQUIRED. PRODUCER IS RESPONSIB$5,000
2019-11-06Job filed: INSTALL OF TEMP PLATFORMS AND TEMPORARY WALLS FOR ENDEAVOR GALA, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. ALL EQUIPMENT REMOVED$5,000
2019-11-06Job filed: INSTALL OF TEMP PLATFORMS AND TEMPORARY WALLS FOR ENDEAVOR GALA, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. ALL EQUIPMENT REMOVED$5,000
2019-11-06Permit AL — ISSUED
2019-11-06Permit AL — ISSUED
2019-11-04Job filed: 19_915-Digital Realty Marketplace a conference with food and beverage. For invited guests only.
2019-11-01Job filed: INSTALL OF TEMP PLATFORMS AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES, FOR DIGITAL REALTY. TPA PERMIT IS REQUIRED. PRODUCER IS RESPON$5,000
2019-11-01Job filed: INSTALL OF TEMP PLATFORMS AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES, FOR DIGITAL REALTY. TPA PERMIT IS REQUIRED. PRODUCER IS RESPON$5,000
2019-11-01Permit AL — ISSUED
2019-10-29Job filed: 19_905 - Art Walk - art show and auction with food and beverage for invited guests only.
2019-10-28Job filed: 19_877 - Riverstone - Conference with food and beverage for invited guests only. Two layouts for the fifth floor.
2019-10-24Job filed: INSTALL OF TEMP PLATFORMS, AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES, FOR RIVERSTONE ANNUAL CONFERENCE. TPA PERMIT IS REQUIRED. PRO$5,000
2019-10-24Job filed: INSTALL OF TEMP PLATFORMS, AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES, FOR RIVERSTONE ANNUAL CONFERENCE. TPA PERMIT IS REQUIRED. PRO$5,000
2019-10-24Permit AL — ISSUED
2019-10-21Job filed: 19_900-Robin Hood - Investors Conference with food and beverage. For invited guests only.
2019-10-18Job filed: INSTALL OF TEMP PLATFORMS AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES, FOR ROBIN HOOD INVESTORS CONFERENCE. TPA PERMIT IS REQUIRED. PR$5,000
2019-10-18Permit AL — ISSUED
2019-10-17Job filed: 19_899-SALESFORCE - Data conference with food and beverage for invited guests only.
2019-10-16Job filed: INSTALL OF TEMP PLATFORM,NO ALTERATIONS TO EXIST STRUCTURES, FOR SALESFORCE AT SPRING STUDIOS. TPA PERMIT IS REQUIRED.PRODUCER IS RESPONSIBLE TO MONIT$5,000
2019-10-16Job filed: INSTALL OF TEMP PLATFORM,NO ALTERATIONS TO EXIST STRUCTURES, FOR SALESFORCE AT SPRING STUDIOS. TPA PERMIT IS REQUIRED.PRODUCER IS RESPONSIBLE TO MONIT$5,000
2019-10-16Permit AL — ISSUED
2019-10-15Job filed: INSTALL OF TEMP PLATFORMS, TRUSSES, SCENIC ELEMENTS, AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES, FOR CNN CITIZEN. TPA PERMIT IS REQUI$5,000
2019-10-15Job filed: 19_854 - CITIZEN BY CNN - Guest Conference with Food & Beverage, for invited guests only.
2019-10-15Permit AL — ISSUED
2019-10-07Job filed: 19_853-FORCES OF FASHION CONFERENCE FOR INVITED GUESTS ONLY. WITH FOOD AND BEVERAGE. Non simultaneous use of floors. Maximum occupancy in all TPA area
2019-10-04Job filed: INSTALL OF TEMP PLATFORMS, TRUSSES, SCENIC ELEMENTS, AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES,FOR FORCES OF FASHION, TPA PERMIT IS $5,000
2019-10-04Job filed: INSTALL OF TEMP PLATFORMS, TRUSSES, SCENIC ELEMENTS, AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES,FOR FORCES OF FASHION, TPA PERMIT IS $5,000
2019-10-04Job filed: INSTALL OF TEMP PLATFORMS, TRUSSES, SCENIC ELEMENTS, AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES,FOR FORCES OF FASHION, TPA PERMIT IS $5,000
2019-10-04Permit AL — ISSUED
2019-10-01Job filed: 19_827- Art exhibit for mastercard with food and beverage for invited guests only.
2019-09-27Certificate of occupancy Temporary
2019-09-26Job filed: 19_829-Popup bar & restaurants for Priceless with food and beverage. Open to public, monitored occupancy.
2019-09-26Job filed: 19_801-TQ Group - Tech conference for TQ with cocktails. With food and beverage, for invited guests only.
2019-09-24Permit EW — ISSUED
2019-09-24Permit AL — ISSUED
2019-09-23Job filed: INSTALL OF TEMP PLATFORMS, TRUSSES, SCENIC ELEMENTS, AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES, TQ GROUP, TPA PERMIT IS REQUIRED.PRO$5,000
2019-09-19Permit AL — ISSUED
2019-09-16Job filed: 19_727-Cocktails and dinner for Norma Mitzvah. With food and beverage, for invited guests only.
2019-09-11311: Noise - Commercial — Loud Music/Party
2019-09-11Job filed: INSTALL OF TEMP PLATFORMS, TRUSSES, SCENIC ELEMENTS, AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES,NORMA MITZVAH. TPA PERMIT IS REQUIRED$5,000
2019-09-11Permit AL — ISSUED
2019-09-09Job filed: 19_708-Awards Dinner for the Microsoft Advertising Agency. Invited guests only, with food and beverage.
2019-09-06DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
2019-09-06DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
2019-09-06DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
2019-09-06DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
2019-09-06DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
2019-08-30Job filed: 19_675- Fashion trade show for women's clothing. For invited guests only.
2019-08-28Job filed: INSTALL OF TEMP PLATFORMS, NO ALTERATIONS TO EXIST STRUCTURES, FOR MICROSOFT AD AGENCY AWARDS. TPA PERMIT IS REQUIRED. PRODUCER IS RESPONSIBLE TO MONI$5,000
2019-08-28Job filed: INSTALL OF TEMP PLATFORMS, NO ALTERATIONS TO EXIST STRUCTURES, FOR MICROSOFT AD AGENCY AWARDS. TPA PERMIT IS REQUIRED. PRODUCER IS RESPONSIBLE TO MONI$5,000
2019-08-28Permit AL — ISSUED
2019-08-26Job filed: 19_671-Fashion show series, main hub for New York's Fashion Week, for invited guests. Various layouts on 5th & 6th floors. 5th and 6th Floors are not
2019-08-22Cooling tower inspection — violation AH8C
2019-08-22Cooling tower inspection
2019-08-15Job filed: INSTALL OF TEMP TENT, PLATFORMS, AND SCENIC ELEMENTS FOR NYFW THE SHOWS, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. SAPO PERMIT #$5,000
2019-08-15Permit AL — ISSUED
2019-08-02Job filed: TO REPLACE EXISTING HUNG CEILING AT 6TH FLOOR CATERING EATING DRINKING ESTABLISHMENT. NO CHANGE TO EXISTING USE, EGRESS OR OCCUPANCY.$30,000
2019-08-02Permit AL — ISSUED
2019-07-31Asbestos abatement: Removal — JVN Restoration Inc.
2019-07-31Asbestos abatement: Removal — JVN Restoration Inc.
2019-07-31Permit AL — ISSUED
2019-07-26Job filed: TO RENOVATE EXISTING OFFICE SPACE AT PART OF 7TH FLOOR. NEW DRY WALL AND GLASS PARTITIONS. MECHANICAL AND SPRINKLER MODIFICATIONS WILL BE FILED UNDER $55,000
2019-07-08Job filed: 19_570- Fashion trade show for Men's clothing. For invited guests only.
2019-07-08Job filed: 19_587- Popup bar & restaurants for Beyond Food with food and beverage. Open to public, monitored occupancy. 5:00P - 12:30A Each Day
2019-07-08Job filed: INSTALL OF TEMP PLATFORMS, TRUSSES, SCENIC ELEMENTS, AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES,FOR BEYOND FOOD. TPA PERMIT IS REQUIR$5,000
2019-07-08Permit AL — ISSUED
2019-07-03Job filed: 19_574- Gala with cocktails, dinner, and awards ceremony for Formula E. With food and beverage for invited guests only.
2019-07-03Job filed: INSTALL OF TEMP PLATFORMS, AND SCENIC ELEMENTS, NO ALTERATIONS TO EXIST STRUCTURES, FOR FORMULA E GALA,TPA PERMIT IS REQUIRED. PRODUCER IS RESPONSIBL$5,000
2019-06-25Certificate of occupancy Temporary
2019-06-20Job filed: 19_489- Trade show for beauty products with food and beverage for invited guests only.
2019-06-19Permit AL — ISSUED
2019-06-19Permit EW — ISSUED
2019-06-18Job filed: 19_494 - Egg Conference for invited guests only with food and beverage.
2019-06-18Permit AL — ISSUED
2019-06-14Job filed: 19_538- Cocktail party for iHeart Radio with food and beverage for invited guests only.
2019-06-14Job filed: INSTALL INTERIOR NON-BEARING PARTITIONS AT 5TH FLOOR OFIICE SPACE. NO CHANGE ON EXISTING USE, EGRESS, OR OCCUPANCY.$18,000
2019-06-14Job filed: INSTALL NON-BEARING INTERIOR PARTITIONS AT 7TH FLOOR MEZZANINE NORTH LOUNGE ROOM. NO CHANGE ON EXISTING USE, EGRESS, OR OCCUPANCY.$8,000
2019-06-12Job filed: 19_494 - Egg Conference for invited guests only with food and beverage.
2019-06-12Job filed: INSTALL OF TEMP PLATFORMS AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES, FOR THE NO CANNES DO EVENT. TPA PERMIT IS REQUIRED. PRODUCER I$5,000
2019-06-12Permit AL — ISSUED
2019-06-08311: Noise - Commercial — Loud Music/Party
2019-06-08311: Noise - Commercial — Loud Music/Party
2019-06-07Job filed: 19_489- Trade show for beauty products with food and beverage for invited guests only.
2019-06-05Job filed: INSTALL OF TEMP PLATFORM AND BOOTHS,NO ALTERATIONS TO EXIST STRUCTURES, FOR EGG CONFERENCE. TPA PERMIT IS REQUIRED. PRODUCER IS RESPONSIBLE TO MONITOR$5,000
2019-06-05Permit AL — ISSUED
2019-05-22Job filed: 19_465-Tanenbaum wedding ceremony with cocktail, dinner and after party. Food and beverage event with invited guests only
2019-05-22Job filed: INSTALL OF TEMP PLATFORMS, TRUSSES, AND EVENT SPECIFIC SCENIC PIECES , NO ALTERATIONS TO EXIST STRUCTURES, FOR THE TANEBAUM WEDDING IN MAY 2019. TPA $5,000
2019-05-22Permit AL — ISSUED
2019-05-21Job filed: 19_437- Product launch with food and beverage for invited guests only.
2019-05-17Job filed: INSTALL OF TEMP PLATFORMS, BLEACHERS, SCENIC EXHIBITS, AND PRODUCTION EQUIPMENT,NO ALTERATIONS TO EXIST STRUCTURES,FOR UNBLUSH: A PLACE TO TALK DESIRE$5,000
2019-05-17Permit AL — ISSUED
2019-05-15311: Sewer — Sewer Odor (SA2)
2019-05-15311: Sewer — Catch Basin Clogged/Flooding (Use Comments) (SC)
2019-05-14Job filed: 19_402- WSJ Dow Jones F.O.E. - Conference with food and beverage. Invited guests only. Two layouts for the 6th floor, same occupancy and number of fir
2019-05-10Permit AL — ISSUED
2019-05-08Job filed: INSTALL OF TEMP PLATFORMS, SCENIC ELEMENTS AND PRODUCTION EQUIPMENT, NO ALTERATIONS TO EXIST STRUCTURES,WSF DOW JONES F.O.E.,TPA PERMIT IS REQUIRED. P$5,000
2019-05-06Job filed: 19_377 - Two day conference with individual exhibits & cocktails, for invited persons only with food and beverage. No More than 380 persons in all TPA
2019-05-02Job filed: Conference and cocktails event for invited guests only, with food and beverage.
2019-05-01Permit AL — ISSUED
2019-04-30311: Taxi Complaint — Driver Complaint - Non Passenger
2019-04-30DOB violation FISPNRF: FAILED TO FILE FISP CYCLE 8C TECHNICAL REPORT BY 02/21/2019
2019-04-30Job filed: Spring Solstice summer 2019 roof outdoor lounge
2019-04-30Job filed: INSTALL OF TEMP PLATFORMS, PRODUCTION EQUIPMENT, AND SCENIC ELEMENTS. NO ALTERATIONS TO EXIST STRUCTURES, FOR ACCENTURE CONFERENCE IN MAY 2019. TPA PE$5,000
2019-04-30Permit AL — ISSUED
2019-04-29Job filed: INSTALL OF TEMP PLATFORM & PRODUCTION EQUIPMENT, NO ALTERATIONS TO EXIST STRUCTURES, FOR NAMELY H.R REDEFINED IN MAY 2019. TPA PERMIT IS REQUIRED.$5,000
2019-04-27311: Street Light Condition — Lamppost Leaning
2019-04-26Job filed: 19_338-Runway Fashion Show with food and beverage for invited guests only.
2019-04-25Job filed: 19_316-Tribeca Film Festival Events on the 6th Floor of the venue with multiple alternate layouts including lounges, theater seating and exhibit areas
2019-04-24Job filed: INSTALL OF TEMP PLATFORM,NO ALTERATIONS TO EXIST STRUCTURES, FOR THE PRATT RUNWAY SHOW IN MAY 2019. TPA PERMIT IS REQUIRED. PRODUCER IS RESPONSIBLE T$5,000
2019-04-24Permit AL — ISSUED
2019-04-23Job filed: 19_364-Fundraiser with dinner and cocktails, for invited guests only, with food and beverage.
2019-04-22Job filed: 19_316-Tribeca Film Festival Events including exhibit and cocktails areas. For invited/ticketed guests only, with food and beverage.
2019-04-18Job filed: 19_316-Tribeca Film Festival Events on the 6th Floor of the venue with multiple alternate layouts including lounges, theater seating and exhibit areas
2019-04-18Job filed: 19_289-Sponsor event with theater and lounge for Bvlgari. For invited guests only with food and beverage.
2019-04-18Permit EW — ISSUED
2019-04-17Job filed: 19_277-Conference with exhibit area for invited guests only. Event with food and beverage. Non-simultaneous use of floors.
2019-04-16Job filed: INSTALL OF TEMP PLATFROMS AND SCENIC ELEMENTS,NO ALTERATIONS TO EXIST STRUCTURES, FOR TRIBECA FILM FESTIVAL EVENTS, APRIL AND MAY 2019. TPA PERMIT IS $5,000
2019-04-16Permit AL — ISSUED
2019-04-16Permit EW — ISSUED
2019-04-09DOB violation E:
2019-04-08DOB violation E:
2019-04-08DOB violation E:
2019-04-08DOB violation E:
2019-04-08DOB violation E:
2019-04-08DOB violation E:
2019-04-05Facade (LL11) filing, cycle 8: SWARMP
2019-04-05DOB violation EVCAT1: VIOLATION ISSUED TO ELEVATOR - FAILURE TO FILE CATEGORY 1 2017 INSPECTION/TEST
2019-04-05DOB violation EVCAT1: VIOLATION ISSUED TO ELEVATOR - FAILURE TO FILE CATEGORY 1 2017 INSPECTION/TEST
2019-04-05DOB violation EVCAT1: VIOLATION ISSUED TO ELEVATOR - FAILURE TO FILE CATEGORY 1 2017 INSPECTION/TEST
2019-04-05DOB violation EVCAT1: VIOLATION ISSUED TO ELEVATOR - FAILURE TO FILE CATEGORY 1 2017 INSPECTION/TEST
2019-04-01Job filed: 19_241-Conference and exhibit area, with food and beverage for invited guests only. Non-Simultaneous use of 5th & 6th floor. 7th floor in use at all t
2019-03-29Job filed: INSTALL OF TEMP PLATFORM,NO ALTERATIONS TO EXIST STRUCTURES,FOR WORKFUSION IN APRIL 2019,TPA PERMIT IS REQUIRED. PRODUCER IS RESPONSIBLE TO MONITOR SI$5,000
2019-03-29Permit AL — ISSUED
2019-03-25Job filed: TO INSTALL MECHANICAL FIRE DAMPERS IN EXISTING DUCTS$8,000
2019-03-25Job filed: TO REPLACE EXISTING FIREPROOF PARTITIONS OF THE PASSAGEWAY BETWEEN STAIR G AND LOBBY ON SOUTH WEST CORNER OF 1ST FLOOR.$14,000
2019-03-25Job filed: 19_218-Event with conference and exhibit display reception, for invited guests only.
2019-03-22Job filed: INSTALL OF TEMP PLATFORMS AND SCENIC WALLS,NO ALTERATIONS TO EXIST STRUCTURES, FOR LEGO ON APRIL 2, TPA PERMIT IS REQUIRED. PRODUCER IS RESPONSIBLE TO$5,000
2019-03-22Permit AL — ISSUED
2019-03-21Certificate of occupancy Temporary
2019-03-19Permit PL — ISSUED
2019-03-13Job filed: 19_176- Turner Sales Conference with food and beverage for invited guests. Various layouts on 5th floor. 5th & 6th Floors are not occupied simultaneou
2019-03-08Job filed: TO INSTALL NEW SPRINKLER HEADS AT 6TH, 7TH, AND 7TH MEZZ LEVELS FOR A FIRE SEPARATION WATER CURTAIN SYSTEM PROTECTING EXISTING GLASS PARTITIONS. NO CH$15,500
2019-03-04Job filed: 19_176- Turner Sales Conference with food and beverage for invited guests. Various layouts on 5th floor. 5th & 6th Floors are not occupied simultaneou
2019-02-28Job filed: INSTALL OF TEMP PLATFORMS,NO ALTERATIONS TO EXIST STRUCTURES, FOR TURNER BROADCASTING SALES EVENT AT SPRING STUDIOS. TPA PERMIT IS REQUIRED. PRODUCE$5,000
2019-02-28Permit AL — ISSUED
2019-02-25Permit EW — ISSUED
2019-02-21Job filed: 19_146- Standing only art fair with invited guests only.
2019-02-20Job filed: RELOCATE BATHROOM WALLS AND NEW PLUMBING FIXTURES AT 2ND FLOOR OFFICE. NEW PANTRY AND LIGHTING. NO CHANGE TO EXISTING USE, OCCUPANCY OR EGRESS.$73,000
2019-02-20Job filed: RELOCATE BATHROOM WALLS AND NEW PLUMBING FIXTURES AT 2ND FLOOR OFFICE. NEW PANTRY AND LIGHTING. NO CHANGE TO EXISTING USE, OCCUPANCY OR EGRESS.$73,000
2019-02-11311: Recycling Enforcement — ER1 Resident Recyc. (Owner/Manager
2019-02-08Job filed: 19_117 Fashion show layout part of series, main hub for New York's Fashion Week, for invited guests.
2019-02-07Job filed: 19_117 Fashion show layout part of series, main hub for New York's Fashion Week, for invited guests.
2019-02-05Job filed: Women's wear trade show, for invited guests only with food and beverage.
2019-02-01Job filed: Fashion show series, main hub for New York's Fashion Week, for invited guests. Various layouts on 5th & 6th floors. 5th and 6th Floors are not occupie
2019-01-30Job filed: INSTALL OF TEMP TENT, PLATFORMS, AND SCENIC ELEMENTS,NO ALTERATIONS TO EXIST STRUCTURES, FOR NYFW: THE SHOWS AT SPRING STUDIOS. SAPO PERMIT IS REQUIRE$5,000
2019-01-30Permit AL — ISSUED
2019-01-29Job filed: AFA 19_048 Partner meeting divided into conference and dinning portions for Goldman Sachs. For invited guests only, with food and beverage. Max occupa
2019-01-25Job filed: No Work
2019-01-25Job filed: No Work
2019-01-24Job filed: No Work
2019-01-24Job filed: No Work
2019-01-24Permit AL — ISSUED
2019-01-22Job filed: INSTALL OF TEMP PLATFORMS AND RISERS, NO ALTERATIONS TO EXIST STRUCTURES, FOR GS GPM 2019. TPA PERMIT IS REQUIRED. PROD IS RESPONSIBLE TO MONITOR SITE$5,000
2019-01-16311: Street Condition — Pothole
2019-01-10Job filed: Trade Show
2018
2018-12-26FDNY inspection (RISK)
2018-12-24Certificate of occupancy Temporary
2018-12-19Job filed: Wedding with ceremony and reception
2018-12-18Job filed: INSTALL OF TEMP PLATFORM, NO ALTERATIONS TO EXIST STRUCTURES, CAPLAN WEDDING. TPA PERMIT IS REQUIRED. PRODUCER IS RESPONSIBLE TO MONITOR SITE SAFETY &$5,000
2018-12-18Permit AL — ISSUED
2018-12-11311: Taxi Complaint — Driver Complaint
2018-12-07311: Noise - Commercial — Car/Truck Horn
2018-11-30Permit AL — ISSUED
2018-11-28Job filed: INSTALL OF TEMP PLATFORM,NO ALTERATIONS TO EXIST STRUCTURES, FOR BUSINESS INSIDER AT SPRING STUDIOS, ON DEC 3 TO 4. TPA PERMIT IS REQUIRED. PRODUCER $5,000
2018-11-28Job filed: INSTALL OF TEMP PLATFORM,NO ALTERATIONS TO EXIST STRUCTURES, FOR BUSINESS INSIDER AT SPRING STUDIOS, ON DEC 3 TO 4. TPA PERMIT IS REQUIRED. PRODUCER $5,000
2018-11-20311: Water System — Hydrant Defective (WC2)
2018-11-20Job filed: INSTALL OF TEMP PLATFORM, NO ALTERATIONS TO EXIST STRUCTURES, FOR ENDEAVOR 2018 AT SPRING STUDIOS ON NOV 29. TPA PERMIT IS REQUIRED. PRODUCER IS RE$5,000
2018-11-20Permit AL — ISSUED
2018-11-13Job filed: INSTALL OF TEMP PLATFORMS AND SCENIC ELEMENTS FOR DE SHAW CONFERENCE SCHEDULED ON NOVEMBER 14, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS R$5,000
2018-11-13Job filed: INSTALL OF TEMP PLATFORMS AND SCENIC ELEMENTS FOR DE SHAW CONFERENCE SCHEDULED ON NOVEMBER 14, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS R$5,000
2018-11-13Permit AL — ISSUED
2018-11-05Job filed: INSTALL OF TEMP PLATFORMS AND SCENIC ELEMENTS FOR SENATORS CONFERENCE SCHEDULED ON NOVEMBER 8, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS R$5,000
2018-11-05Permit AL — ISSUED
2018-10-31Job filed: INSTALL OF TEMP PLATFORMS FOR WOMAN OF THE YEAR ON NOVEMBER 11 AND 12, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. PRODUCER IS RES$5,000
2018-10-31Job filed: INSTALL OF TEMP PLATFORMS FOR WOMAN OF THE YEAR ON NOVEMBER 11 AND 12, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. PRODUCER IS RES$5,000
2018-10-31Permit AL — ISSUED
2018-10-30311: Street Condition — Pothole
2018-10-26Job filed: INSTALL OF TEMP PLATFORMS FOR RIVERSTONE ANNUAL MEETING ON NOVEMBER 6, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. ALL EQUIPMENT R$5,000
2018-10-26Permit AL — ISSUED
2018-10-25Job filed: INSTALL OF TEMP PLATFORM FOR ROBIN HOOD ON OCTOBER 29 & 30, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. ALL EQUIPMENT REMOVED $5,000
2018-10-25Permit AL — ISSUED
2018-10-23Permit AL — ISSUED
2018-10-19Job filed: INSTALL OF TEMP PLATFORMS AND TRELLIS STRUCTURE FOR MEDIDATA SCHEDULED ON OCTOBER 24, 2018, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQU$5,000
2018-10-19Job filed: INSTALL OF TEMP PLATFORMS AND TRELLIS STRUCTURE FOR MEDIDATA SCHEDULED ON OCTOBER 24, 2018, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQU$5,000
2018-10-18311: Noise - Commercial — Loud Music/Party
2018-10-09Job filed: INSTALL OF TEMP SCENIC WALLS AND SCENIC STRUCTURES FOR PELOTON TREAD SCHEDULED ON OCTOBER 18 TO 20, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT$5,000
2018-10-09Job filed: INSTALL OF TEMP SCENIC WALLS AND SCENIC STRUCTURES FOR PELOTON TREAD SCHEDULED ON OCTOBER 18 TO 20, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT$5,000
2018-10-09Permit AL — ISSUED
2018-10-01Job filed: INSTALL OF TEMP PLATFORMS AND SCENIC STRUCTURE FOR SLACK ROADSHOW SCHEDULED ON OCTOBER 3RD AND 4TH, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT$5,000
2018-10-01Permit AL — ISSUED
2018-09-27Job filed: INSTALL OF TEMP PLATFORMS FOR GOOGLE PRODUCT LAUNCH SCHEDULED ON OCTOBER 9TH TO 11TH, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. $5,000
2018-09-27Job filed: INSTALL OF TEMP PLATFORMS FOR GOOGLE PRODUCT LAUNCH SCHEDULED ON OCTOBER 9TH TO 11TH, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. $5,000
2018-09-27Permit EW — ISSUED
2018-09-27Permit EW — ISSUED
2018-09-27Permit AL — ISSUED
2018-09-27Permit EW — ISSUED
2018-09-14Job filed: INSTALL OF TEMP PLATFORMS FOR TRIBECA TV FEST 2018 SCHEDULED ON SEPTEMBER 20-23, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. ALL E$5,000
2018-09-14Permit AL — ISSUED
2018-09-10311: Recycling Enforcement — ER5 Comm. Recyc. (Bldg Mgmt)
2018-09-08311: For Hire Vehicle Complaint — Car Service Company Complaint
2018-09-07Permit PL — ISSUED
2018-08-29Permit AL — ISSUED
2018-08-28Job filed: INSTALL OF TEMP TENT, PLATFORMS, AND SCENIC ELEMENTS FOR NYFW THE SHOWS SCHEDULED SEPTEMBER 2018 NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS$5,000
2018-08-28Job filed: INSTALL OF TEMP TENT, PLATFORMS, AND SCENIC ELEMENTS FOR NYFW THE SHOWS SCHEDULED SEPTEMBER 2018 NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS$5,000
2018-08-28Permit AL — ISSUED
2018-08-27Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR POPUP LOUNGE EVENT AT 6TH FLOOR ON SEPTEMBER 4TH, 2018 TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETIO$6,000
2018-08-27Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR POPUP LOUNGE EVENT AT 6TH FLOOR ON SEPTEMBER 4TH, 2018 TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETIO$6,000
2018-08-27Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR POPUP LOUNGE EVENT AT 6TH FLOOR ON SEPTEMBER 4TH, 2018 TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETIO$6,000
2018-08-27Permit AL — ISSUED
2018-08-23Permit EW — ISSUED
2018-08-23Permit EW — RE-ISSUED
2018-08-14Cooling tower inspection — violation AH8H
2018-08-14Cooling tower inspection — violation AH8D
2018-08-14Cooling tower inspection — violation AH8K
2018-08-14Cooling tower inspection — violation AH8S
2018-08-14Cooling tower inspection — violation AH8F
2018-08-14Cooling tower inspection — violation AH8B
2018-08-14Cooling tower inspection — violation AH8T
2018-08-14Cooling tower inspection — violation AH8W
2018-08-14Cooling tower inspection — violation AH8E
2018-08-14Cooling tower inspection — violation AH8L
2018-08-14Cooling tower inspection — violation AH8A
2018-08-14Cooling tower inspection — violation AH8S
2018-08-14Cooling tower inspection — violation AH8X
2018-08-14Cooling tower inspection — violation AH8C
2018-08-14Cooling tower inspection — violation AH8E
2018-08-14Cooling tower inspection — violation AH8U
2018-08-14Cooling tower inspection — violation AH8R
2018-08-14Cooling tower inspection — violation AH8Q
2018-08-14Cooling tower inspection — violation AH9C
2018-08-14Cooling tower inspection — violation AH8D
2018-07-19Certificate of occupancy Temporary
2018-07-13Rodent inspection: Passed
2018-07-11311: Water System — Hydrant Running (WC3)
2018-07-11Permit AL — ISSUED
2018-07-10Job filed: INSTALL OF TEMP PLATFORM FOR FORMULA E SCHEDULED ON AUGUST 9TH, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. PRODUCER IS RESPONSIBL$5,000
2018-07-10Job filed: INSTALL OF TEMP PLATFORM FOR FORMULA E SCHEDULED ON AUGUST 9TH, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. PRODUCER IS RESPONSIBL$5,000
2018-07-05Job filed: INSTALL OF TEMP PLATFORMS FOR DATADOG DASH CONFERENCE 2018 SCHEDULED ON JULY 11 & 12, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIR$5,000
2018-07-05Permit AL — ISSUED
2018-06-26Permit AL — ISSUED
2018-06-22Job filed: INSTALL OF TEMP PLATFORMS FOR CHOU WEDDING AT SPRING STUDIOS ON JUNE 29. NO ALTERATIONS TO EXIST STRUCTURES. TPA PERMIT IS REQUIRED. PRODUCER IS RESP$5,000
2018-06-22Job filed: INSTALL OF TEMP PLATFORMS FOR CHOU WEDDING AT SPRING STUDIOS ON JUNE 29. NO ALTERATIONS TO EXIST STRUCTURES. TPA PERMIT IS REQUIRED. PRODUCER IS RESP$5,000
2018-06-13Job filed: INSTALL OF TEMP PLATFORMS FOR ONE SOURCE CORPORATE EVENT SCHEDULED ON JUNE 20TH, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. ALL E$5,000
2018-06-13Permit AL — ISSUED
2018-06-12Job filed: INSTALL OF TEMP PLATFORM AND INDOOR INTERIOR DISPLAY CASES FOR TWO SIGMA EVENT AT SPRING STUDIO, 50 VARICK ST, ON JUNE 19TH. NO ALTERATIONS TO EXIST S$5,000
2018-06-12Job filed: INSTALL OF TEMP PLATFORMS FOR ECKHART AWARDS SCHEDULED ON JUNE 14TH, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. ALL EQUIPMENT REM$5,000
2018-06-12Job filed: INSTALL OF TEMP PLATFORMS FOR ECKHART AWARDS SCHEDULED ON JUNE 14TH, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. ALL EQUIPMENT REM$5,000
2018-06-12Job filed: INSTALL OF TEMP PLATFORM AND INDOOR INTERIOR DISPLAY CASES FOR TWO SIGMA EVENT AT SPRING STUDIO, 50 VARICK ST, ON JUNE 19TH. NO ALTERATIONS TO EXIST S$5,000
2018-06-12Permit AL — ISSUED
2018-06-12Permit AL — ISSUED
2018-06-11311: Derelict Vehicle — With License Plate
2018-06-11311: Derelict Vehicle — With License Plate
2018-06-08Job filed: INSTALL OF TEMP PLATFORM FOR DAVID MONN 80 BIRTHDAY SCHEDULED ON JUNE 18, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED, SAPO PERMIT $5,000
2018-06-08Permit AL — ISSUED
2018-05-30Job filed: INSTALL OF TEMP PLATFORMS AND EXHIBITS FOR LANE WEDDING SCHEDULED ON JUNE 2, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED, SAPO PERM$5,000
2018-05-30Permit AL — ISSUED
2018-05-08Job filed: INSTALL OF TEMP PLATFORM FOR UNIVISION SCHEDULED ON MAY 14 AND 15, 2018 , NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. ALL EQUIPMEN$5,000
2018-05-08Job filed: INSTALL OF TEMP PLATFORM FOR UNIVISION SCHEDULED ON MAY 14 AND 15, 2018 , NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. ALL EQUIPMEN$5,000
2018-05-08Permit AL — ISSUED
2018-05-07Permit AL — ISSUED
2018-05-03Job filed: INSTALL OF TEMP PLATFORM AND SCENIC FLATS FOR PRATT RUNWAY SHOW SCHEDULED ON MAY 3, 2018, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIR$5,000
2018-05-03Permit AL — ISSUED
2018-05-03Permit AL — ISSUED
2018-05-02Job filed: INSTALL OF TEMP PLATFORM FOR UMG SLEEP SCHEDULED ON MAY 4 AND 5, 2018 , NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. ALL EQUIPMENT $5,000
2018-05-02Job filed: INSTALL OF TEMP PLATFORM FOR UMG SLEEP SCHEDULED ON MAY 4 AND 5, 2018 , NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. ALL EQUIPMENT $5,000
2018-05-02Permit EW — ISSUED
2018-04-27Permit EW — ISSUED
2018-04-26Job filed: INSTALL OF TEMP PLATFORM AND SEATING RISERS FOR VICE NEWFRONT 2018 SCHEDULED ON MAY 4, 2018 , NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS RE$5,000
2018-04-26Job filed: INSTALL OF TEMP PLATFORM AND SEATING RISERS FOR VICE NEWFRONT 2018 SCHEDULED ON MAY 4, 2018 , NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS RE$5,000
2018-04-26Job filed: INSTALL OF TEMP PLATFORMS FOR WSJ DOW JONES FUTURE OF EVERYTHING FESTIVAL SCHEDULED ON MAY 8 TO 10, 2018, NO ALTERATION OF EXISTING STRUCTURES, A TPA $5,000
2018-04-26Job filed: INSTALL OF TEMP PLATFORM AND SEATING RISERS FOR VICE NEWFRONT 2018 SCHEDULED ON MAY 4, 2018 , NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS RE$5,000
2018-04-26Permit AL — ISSUED
2018-04-23Certificate of occupancy Temporary
2018-04-16Permit EW — ISSUED
2018-04-16Permit EW — ISSUED
2018-04-13Job filed: CONSTRUCT INTERIOR NON-BEARING PARTITIONS IN EXISTING OFFICE SPACE AT PARTIAL SOUTH EAST AREA OF 7TH FLOOR (PHASE II). NO CHANGE TO EXISTING USE, EGRE$75,000
2018-04-13Job filed: CONSTRUCT INTERIOR NON-BEARING PARTITIONS IN EXISTING OFFICE SPACE AT PARTIAL SOUTH EAST AREA OF 7TH FLOOR (PHASE II). NO CHANGE TO EXISTING USE, EGRE$75,000
2018-04-13Job filed: MODIFICATION OF EXISTING MECHANICAL DUCTS AND REMOVE PL FIXTURE$19,000
2018-04-13Job filed: MODIFICATION OF EXISTING FIRE ALARM SYSTEM IN EXISTING OFFICE SPACE AT PARTIAL SOUTH EAST 7TH FLOOR AREA.$9,000
2018-04-13Job filed: MODIFICATION OF EXISTING SPRINKLER SYSTEM IN EXISTING OFFICE SPACE AT PARTIAL SOUTH EAST 7TH FLOOR AREA (PHASE II).$8,000
2018-04-12Job filed: INSTALL OF TEMP PLATFORM AND TRUSSES FOR IMG LIVE MARRIOT HOTEL SCHEDULED ON APRIL 16TH, 2018, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS R$5,000
2018-04-12Job filed: INSTALL OF TEMP PLATFORM AND TRUSSES FOR IMG LIVE MARRIOT HOTEL SCHEDULED ON APRIL 16TH, 2018, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS R$5,000
2018-04-12Permit AL — ISSUED
2018-04-10Job filed: INSTALL OF TEMP EXHIBITS AND PLATFORM FOR THE TRIBECA FILM FESTIVAL AT SPRING SCHEDULED ON APRIL 19 TO APRIL 29, 2018, NO ALTERATION OF EXISTING STRUC$5,000
2018-04-10Job filed: INSTALL OF TEMP EXHIBITS AND PLATFORM FOR THE TRIBECA FILM FESTIVAL AT SPRING SCHEDULED ON APRIL 19 TO APRIL 29, 2018, NO ALTERATION OF EXISTING STRUC$5,000
2018-04-10Permit AL — ISSUED
2018-04-06Job filed: INSTALL OF TEMP TENT PLATFORM FOR VANITY FAIR EVENT ON APRIL 12, A TPA IS REQUIRED, NO ALTERATIONS TO EXIST STRUCTURES.PRODUCER IS RESPONSIBLE TO MONI$5,000
2018-04-06Job filed: INSTALL OF TEMP TENT PLATFORM FOR VANITY FAIR EVENT ON APRIL 12, A TPA IS REQUIRED, NO ALTERATIONS TO EXIST STRUCTURES.PRODUCER IS RESPONSIBLE TO MONI$5,000
2018-04-06Permit AL — ISSUED
2018-03-26DOB violation E:
2018-03-26DOB violation E:
2018-03-26DOB violation E:
2018-03-26DOB violation E:
2018-03-26DOB violation E:
2018-03-26DOB violation E:
2018-03-22Permit EW — ISSUED
2018-03-21Permit EW — ISSUED
2018-03-21Permit EW — ISSUED
2018-03-21Permit EW — ISSUED
2018-03-20Job filed: INSTALL OF TEMP PLATFORMS, NO ALTERATIONS TO EXIST STRUCTURES, FOR SAKHAI WEDDING SCHEDULED FOR MARCH 24, 2018. A TPA PERMIT IS REQUIRED. PRODUCER IS $5,000
2018-03-20Permit AL — ISSUED
2018-03-09Job filed: INSTALL OF TEMP PLATFORMS FOR TURNER BROADCAST 2018 SCHEDULED ON MARCH 20TH & MARCH 21ST , NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS R$5,000
2018-03-09Permit AL — ISSUED
2018-03-02Job filed: INSTALL OF TEMP PLATFORM FOR SPOTIFY EVENT SCHEDULED ON MARCH 15, 2018 , NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. ALL EQUIPMENT$5,000
2018-03-02Job filed: INSTALL OF TEMP PLATFORM FOR SPOTIFY EVENT SCHEDULED ON MARCH 15, 2018 , NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. ALL EQUIPMENT$5,000
2018-03-02Permit AL — ISSUED
2018-02-12311: Noise - Commercial — Loud Music/Party
2018-01-31Permit EW — ISSUED
2018-01-30Certificate of occupancy Temporary
2018-01-29311: Noise - Commercial — Loud Music/Party
2018-01-29311: Noise - Commercial — Loud Music/Party
2018-01-26DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST
2018-01-26DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST
2018-01-26DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST
2018-01-26DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST
2018-01-26DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST
2018-01-25Job filed: HEREBY FILING DRAWINGS TO CREATE AN OPENING OF EXISTING NON LOAD BEARING PARTITION. THIS APPLICATION DO NOT REQUIRE A NEW OR AMENDED CERTIFICATE OF OC$5,000
2018-01-22Job filed: INSTALL OF TEMP. EXT. TENT AND INT. PLAT. AND PROD. EQUIP. FOR IMG NY FASHION WEEK - THE SHOW SCHEDULED ON FEB 8 TO FEB 14 2018 , NO ALTERATION OF EXI$5,000
2018-01-22Permit AL — ISSUED
2018-01-17Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR BECKER MITZVAH EVENT ON JANUARY 20TH, 2018 TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETION. PRODUCE$4,500
2018-01-17Permit AL — ISSUED
2018-01-16Job filed: INSTALL OF TEMP EXTERIOR TENT AND INTERIOR PLATFORMS, NO ALT TO EXIST STRUCTURES, FOR UMG GRAMMY AWARD PARTY SCHEDULED FOR JAN 27 TO 28, 2018. SAPO PE$5,000
2018-01-16Job filed: INSTALL OF TEMP EXTERIOR TENT AND INTERIOR PLATFORMS, NO ALT TO EXIST STRUCTURES, FOR UMG GRAMMY AWARD PARTY SCHEDULED FOR JAN 27 TO 28, 2018. SAPO PE$5,000
2018-01-16Permit AL — ISSUED
2018-01-11AALR — from SERIES TRS OF LADDER CAPITAL FINANCE II ; LADDER CAPITAL FINANCE II LLC to WELLS FARGO BANK, NATIONAL ASSOCIATION,
2018-01-11Mortgage assigned — from SERIES TRS OF LADDER CAPITAL FINANCE II ; LADDER CAPITAL FINANCE II LLC to WELLS FARGO BANK, NATIONAL ASSOCIATION,
2018-01-11AALR — from SERIES TRS OF LADDER CAPITAL FINANCE II ; LADDER CAPITAL FINANCE II LLC to WELLS FARGO BANK, NATIONAL ASSOCIATION,
2018-01-11Mortgage assigned — from SERIES TRS OF LADDER CAPITAL FINANCE II ; LADDER CAPITAL FINANCE II LLC to WELLS FARGO BANK, NATIONAL ASSOCIATION,
2018-01-11311: Noise - Commercial — Loud Talking
2018-01-08Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR LEVI"S EVENT ON JANUARY 10TH, 2018 TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETION. PRODUCER IS RESPO$8,000
2018-01-08Permit AL — ISSUED
2017
2017-12-14311: Noise - Commercial — Loud Music/Party
2017-12-14311: Noise - Commercial — Loud Music/Party
2017-12-12311: Noise - Commercial — Loud Music/Party
2017-12-08Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR ESTEE LAUDER LIPS TO ENVY EVENT ON DEC. 12TH, 2017, TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETION$6,000
2017-12-08Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR BILLBOARD HOLIDAY PARTY EVENT ON DEC. 14TH, 2017, TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETION. $5,000
2017-12-08Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR ESTEE LAUDER LIPS TO ENVY EVENT ON DEC. 12TH, 2017, TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETION$6,000
2017-12-08Permit AL — ISSUED
2017-12-08Permit AL — ISSUED
2017-12-06311: Noise - Residential — Loud Talking
2017-12-06Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR HILTON HONORS EVENT ON DEC. 9TH, 2017, TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETION. PRODUCER IS R$3,500
2017-12-06Permit AL — ISSUED
2017-12-03311: Noise - Commercial — Banging/Pounding
2017-12-01311: Noise - Commercial — Banging/Pounding
2017-11-28Permit AL — ISSUED
2017-11-24Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR ENDEAVOR BENEFIT GALA EVENT SCHEDULED ON NOV 30TH, 2017. TEMP PLATFORM WILL BE REMOVED UPON EVENT COMPLE$2,000
2017-11-24Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR ENDEAVOR BENEFIT GALA EVENT SCHEDULED ON NOV 30TH, 2017. TEMP PLATFORM WILL BE REMOVED UPON EVENT COMPLE$2,000
2017-11-13Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR MICROSOFT CONNECT EVENT SCHEDULED ON NOV 15TH, 2017. TEMP PLATFORM WILL BE REMOVED UPON EVENT COMPLETION$15,000
2017-11-13Permit AL — ISSUED
2017-11-08Certificate of occupancy Temporary
2017-11-08Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR MEDIDATA CONFERENCE EVENT SCHEDULED ON NOV 8TH, 2017, TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETI$8,000
2017-11-08Permit AL — ISSUED
2017-11-03Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR BAR MITZVAH EVENT SCHEDULED ON NOV 4TH, 2017, TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETION. PRODUC$11,000
2017-11-03Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR BAR MITZVAH EVENT SCHEDULED ON NOV 4TH, 2017, TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETION. PRODUC$11,000
2017-11-03Permit AL — ISSUED
2017-10-31311: Noise - Commercial — Loud Talking
2017-10-20AALR — from TUEBOR TRS II LLC to LADDER CAPITAL FINANCE II LLC; SERIES TRS OF LADDER CAPITAL FINANCE II
2017-10-20Mortgage assigned — from TUEBOR TRS II LLC to SERIES TRS OF LADDER CAPITAL FINANCE II ; LADDER CAPITAL FINANCE II LLC
2017-10-20Mortgage assigned — from TUEBOR TRS II LLC to SERIES TRS OF LADDER CAPITAL FINANCE II ; LADDER CAPITAL FINANCE II LLC
2017-10-20AALR — from TUEBOR TRS II LLC to LADDER CAPITAL FINANCE II LLC; SERIES TRS OF LADDER CAPITAL FINANCE II
2017-10-18311: Noise - Commercial — Loud Music/Party
2017-10-16Permit AL — ISSUED
2017-10-13Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR ROBIN HOOD INVESTMENT CONFERENCE SCHEDULED ON OCT 19TH, 2017, TEMP. PLATFORM WILL BE REMOVED UPON EVENT $8,000
2017-10-13Job filed: TO INSTALL A TEMPORARY INTERIOR PLATFORMS FOR GOD'S LOVE GALA EVENT SCHEDULED ON OCT 16TH, 2017, TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETION.$8,000
2017-10-13Permit AL — ISSUED
2017-10-12Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR ROBIN HOOD INVESTMENT CONFERENCE SCHEDULED ON OCT 19TH, 2017, TEMP. PLATFORM WILL BE REMOVED UPON EVENT CO$8,000
2017-10-12Job filed: TO INSTALL TEMPORARY INTERIOR PLATFORMS FOR ROBIN HOOD INVESTMENT CONFERENCE SCHEDULED ON OCT 19TH, 2017, TEMP. PLATFORM WILL BE REMOVED UPON EVENT CO$8,000
2017-10-12Job filed: TO INSTALL A TEMPORARY INTERIOR PLATFORMS FOR GOD'S LOVE GALA EVENT SCHEDULED ON OCT 16TH, 2017, TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETION.$8,000
2017-10-12Job filed: TO INSTALL A TEMPORARY INTERIOR PLATFORMS FOR GOD'S LOVE GALA EVENT SCHEDULED ON OCT 16TH, 2017, TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETION.$8,000
2017-10-12Permit EW — ISSUED
2017-10-10Job filed: TO INSTALL A TEMPORARY INTERIOR PLATFORMS FOR TIFFANY EVENT SCHEDULED ON OCT 13TH, 2017, TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETION. PRODUC$8,000
2017-10-10Job filed: TO INSTALL A TEMPORARY INTERIOR PLATFORMS FOR TIFFANY EVENT SCHEDULED ON OCT 13TH, 2017, TEMP. PLATFORM WILL BE REMOVED UPON EVENT COMPLETION. PRODUC$8,000
2017-10-04Agreement — from BOARD OF MANAGERS OF 50 VARICK STREET CO to SPRING STUDIOS NEW YORK LLC
2017-10-04Agreement — from BOARD OF MANAGERS OF 50 VARICK STREET CO to VARICK SP, LLC
2017-10-04Agreement — from BOARD OF MANAGERS OF 50 VARICK STREET CO to VARICK SP, LLC
2017-10-04Agreement — from BOARD OF MANAGERS OF 50 VARICK STREET CO to SPRING STUDIOS NEW YORK LLC
2017-09-28Permit EW — ISSUED
2017-09-28Permit EW — ISSUED
2017-09-28Permit EW — ISSUED
2017-09-06Permit AL — ISSUED
2017-09-05Permit AL — ISSUED
2017-09-05Permit AL — ISSUED
2017-09-01Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORMS FOR JEREMY SCOTT SS18 FASHION SHOW SCHEDULED ON SEPT. 8, 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PER$5,000
2017-09-01Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORMS FOR SPRING FUNDRAISER SCHEDULED ON SEPT. 7, 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIR$5,000
2017-09-01Permit AL — ISSUED
2017-08-31Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORMS FOR MICHAEL KORS SS18 SHOW SCHEDULED ON SEPT. 13, 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS $5,000
2017-08-31Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORMS FOR MICHAEL KORS SS18 SHOW SCHEDULED ON SEPT. 13, 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS $5,000
2017-08-29Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORM FOR ZIMMERMAN SS18 RUNWAY SHOW SCHEDULED ON SEPT. 11, 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT $5,000
2017-08-29Permit AL — ISSUED
2017-08-25311: Street Condition — Pothole
2017-08-24AALR — from LADDER CAPITAL FINANCE LLC to TUEBOR TRS II LLC
2017-08-24Mortgage assigned — from LADDER CAPITAL FINANCE LLC to TUEBOR TRS II LLC
2017-08-24AALR — from LADDER CAPITAL FINANCE LLC to TUEBOR TRS II LLC
2017-08-24Mortgage assigned — from LADDER CAPITAL FINANCE LLC to TUEBOR TRS II LLC
2017-08-22311: Illegal Parking — Blocked Sidewalk
2017-08-16SAGE — from VARICK 3 LLC; VARICK 4 LLC to LADDER CAPITAL FINANCE LLC
2017-08-16ADEC — from 50 VARICK STREET CONDOMINIUM
2017-08-16ADEC — from 50 VARICK STREET CONDOMINIUM
2017-08-16TL&R — from COLUMN FINANCIAL,INC.
2017-08-16ADEC — from 50 VARICK STREET CONDOMINIUM
2017-08-16Agreement $77,890,000 — from VARICK 4 LLC; VARICK 3 LLC to LADDER CAPITAL FINANCE LLC$77,890,000
2017-08-16PREL — from COLUMN FINANCIAL,INC. to ARC NY350BL001, LLC; ARC NY120W5701 TRS, LLC; ARC NYWSHST001, LLC; ARC NYCTGRG001, LLC; AR
2017-08-16Mortgage assigned — from COLUMN FINANCIAL,INC. to LADDER CAPITAL FINANCE LLC
2017-08-16Mortgage $26,531,106 — from VARICK 3 LLC; VARICK 4 LLC to LADDER CAPITAL FINANCE LLC$26,531,106
2017-08-16ADEC — from 50 VARICK STREET CONDOMINIUM
2017-08-16TL&R — from COLUMN FINANCIAL,INC.
2017-08-16PREL — from COLUMN FINANCIAL,INC. to ARC NY350BL001, LLC; ARC NY120W5701 TRS, LLC; ARC NYWSHST001, LLC; ARC NYCTGRG001, LLC; AR
2017-08-16Mortgage assigned — from COLUMN FINANCIAL,INC. to LADDER CAPITAL FINANCE LLC
2017-08-16ADEC — from 50 VARICK STREET CONDOMINIUM
2017-08-16Agreement — from LADDER CAPITAL FINANCE LLC to VARICK SP, LLC
2017-08-16Agreement — from LADDER CAPITAL FINANCE LLC to SPRING STUDIOS NEW YORK, LLC
2017-08-16Agreement — from LADDER CAPITAL FINANCE LLC to VARICK SP, LLC
2017-08-16AL&R $77,890,000 — from VARICK 3 LLC; VARICK 4 LLC to LADDER CAPITAL FINANCE LLC$77,890,000
2017-08-16AL&R $77,890,000 — from VARICK 3 LLC; VARICK 4 LLC to LADDER CAPITAL FINANCE LLC$77,890,000
2017-08-16Agreement $77,890,000 — from VARICK 4 LLC; VARICK 3 LLC to LADDER CAPITAL FINANCE LLC$77,890,000
2017-08-16SAGE — from VARICK 3 LLC; VARICK 4 LLC to LADDER CAPITAL FINANCE LLC
2017-08-16Deed $135,000,000 — from 50 VARICK LLC to VARICK 3 LLC; VARICK 4 LLC$135,000,000
2017-08-16Deed $135,000,000 — from 50 VARICK LLC to VARICK 3 LLC; VARICK 4 LLC$135,000,000
2017-08-16Agreement — from LADDER CAPITAL FINANCE LLC to SPRING STUDIOS NEW YORK, LLC
2017-08-16ADEC — from 50 VARICK STREET CONDOMINIUM
2017-08-16Mortgage $26,531,106 — from VARICK 3 LLC; VARICK 4 LLC to LADDER CAPITAL FINANCE LLC$26,531,106
2017-08-16ADEC — from 50 VARICK STREET CONDOMINIUM
2017-08-16Permit EW — ISSUED
2017-08-11Permit AL — ISSUED
2017-08-07Sold for $135,000,000$135,000,000
2017-08-07Deed transfer (nominal price)
2017-08-07Job filed: FILING FOR A FIRE SUPPRESSION SYSTEM. KITCHEN WAS FILED UNDER APPL# 120911996. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$3,000
2017-07-31Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORMS FOR WERTHEIMER/ KATZMAN WEDDING SCHEDULED ON AUGUST 12, 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERM$5,000
2017-07-31Permit AL — ISSUED
2017-07-26Certificate of occupancy Temporary
2017-07-21Rodent inspection: Passed
2017-07-17Permit EW — ISSUED
2017-07-13Job filed: INSTALL OF TEMP PRODUCTION EQUIPMENT AND PLATFORM FOR THE IBM CONFERENCE SCHEDULED ON JULY 17, 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMI$5,000
2017-07-13Permit AL — ISSUED
2017-07-12Permit PL — ISSUED
2017-07-10Job filed: RELOCATE SPRINKLER HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$6,750
2017-07-07Job filed: MODIFY MECHANICAL DUCTWORK AND INSTALL HVAC UNIT(S). INSTALL NEW PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE I$180,000
2017-07-07Job filed: DEMOLISH AND CONSTRUCT INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$175,000
2017-07-07Permit EW — ISSUED
2017-07-07Permit EW — ISSUED
2017-07-05Permit EW — ISSUED
2017-07-05Permit EW — ISSUED
2017-07-05Permit EW — ISSUED
2017-06-21Permit EW — ISSUED
2017-06-21Permit PL — ISSUED
2017-06-19Permit EW — ISSUED
2017-06-16Permit EW — ISSUED
2017-06-14Job filed: MECHANICAL MODIFICATION AND REPLACE EXISTING DUCT WORK. REMOVE PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN $21,000
2017-06-14Job filed: DEMOLISH AND CONSTRUCT INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$300,000
2017-06-13Job filed: INSTALL SPRINKLER HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$59,000
2017-06-13Job filed: INSTALL SPRINKLER HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$59,000
2017-06-13Job filed: ADDITIONS/MODIFICATIONS TO THE EXISTING FIRE ALARM SYSTEM AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$15,000
2017-06-12Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORMS FOR ADOBE 2017 CONFERENCE SCHEDULED ON JUNE 20 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQ$5,000
2017-06-12Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORMS FOR ADOBE 2017 CONFERENCE SCHEDULED ON JUNE 20 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQ$5,000
2017-06-12Permit AL — ISSUED
2017-06-09Job filed: INSTALL OF TEMP INTERIOR PLATFORM AND EXTERIOR TENTS FOR TESS GRAY S BAT MITZVAH SCHEDULED ON JUNE 17 2017, NO ALTERATION OF EXISTING STRUCTURES, A TP$5,000
2017-06-09Job filed: INSTALL OF TEMP INTERIOR PLATFORM AND EXTERIOR TENTS FOR TESS GRAY S BAT MITZVAH SCHEDULED ON JUNE 17 2017, NO ALTERATION OF EXISTING STRUCTURES, A TP$5,000
2017-06-09Permit AL — ISSUED
2017-06-06Permit AL — ISSUED
2017-06-05Job filed: ADDITIONS/MODIFICATIONS TO THE EXISTING FIRE ALARM SYSTEM AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$5,000
2017-06-05Job filed: ADDITIONS/MODIFICATIONS TO THE EXISTING FIRE ALARM SYSTEM AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$5,000
2017-06-05Job filed: ADDITIONS/MODIFICATIONS TO THE EXISTING FIRE ALARM SYSTEM AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$5,000
2017-06-05Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORM FOR FORBES SCHEDULED ON JUNE 13 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. ALL EQUIP$5,000
2017-06-02311: Illegal Parking — Posted Parking Sign Violation
2017-06-01311: Sewer — Catch Basin Clogged/Flooding (Use Comments) (SC)
2017-05-31Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORM FOR WIRED BUSINESS CONFERENCE 2017 SCHEDULED ON JUNE 7 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT$5,000
2017-05-31Permit AL — ISSUED
2017-05-25Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORM FOR HILLEL INTERNATIONAL GALA SCHEDULED ON JUNE 5TH, 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT I$5,000
2017-05-25Permit AL — ISSUED
2017-05-22Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORM FOR ACCELERATION SCHEDULED ON MAY 25TH 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. AL$5,000
2017-05-22Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORM FOR ACCELERATION SCHEDULED ON MAY 25TH 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. AL$5,000
2017-05-22Permit AL — ISSUED
2017-05-18Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORM FOR JOYFUL HEART GALA SCHEDULED ON MAY 22ND 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRE$5,000
2017-05-18Permit AL — ISSUED
2017-05-17Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORM AND CANOPIES FOR THE B. ESSES WEDDING SCHEDULED ON MAY 20TH 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA P$5,000
2017-05-17Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORM AND CANOPIES FOR THE B. ESSES WEDDING SCHEDULED ON MAY 20TH 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA P$5,000
2017-05-17Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORM AND CANOPIES FOR THE B. ESSES WEDDING SCHEDULED ON MAY 20TH 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA P$5,000
2017-05-17Permit AL — ISSUED
2017-05-15Certificate of occupancy Temporary
2017-05-04Permit EW — ISSUED
2017-05-02DOB violation BENCH: FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4
2017-04-28311: Consumer Complaint — Exchange/Refund/Return
2017-04-24Job filed: INSTALL OF TEMP. INT. PLATFORM FOR SPRING STUDIOS EVENTS SCHEDULED ON MAY 4TH 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQUIRED. AL$5,000
2017-04-24Permit AL — ISSUED
2017-04-22311: Street Condition — Pothole
2017-04-20Permit AL — ISSUED
2017-04-18Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORM AND GEODESIC DOME FOR SPRING STUDIOS PLATFORM AND DOME SCHEDULED ON APRIL 21ST, 2017, NO ALTERATION OF EXISTING$5,000
2017-04-18Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORM AND GEODESIC DOME FOR SPRING STUDIOS PLATFORM AND DOME SCHEDULED ON APRIL 21ST, 2017, NO ALTERATION OF EXISTING$5,000
2017-04-18Permit EW — ISSUED
2017-04-18Permit EW — ISSUED
2017-04-18Permit EW — ISSUED
2017-04-13Permit AL — ISSUED
2017-04-11Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORMS FOR IWC TRIBECA FILM FESTIVAL 2017 SCHEDULED ON APRIL 20TH, 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA $5,000
2017-04-07Job filed: INSTALL OF TEMPORARY PLATFORMS FOR OSK MARKETING ? AUTO LAUNCH SCHEDULED ON APRIL 11TH, 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS RE$5,000
2017-04-07Job filed: INSTALL OF TEMPORARY PLATFORMS FOR OSK MARKETING ? AUTO LAUNCH SCHEDULED ON APRIL 11TH, 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS RE$5,000
2017-04-07Permit AL — ISSUED
2017-03-27DOB violation E:
2017-03-22Cooling tower inspection — violation AH9C
2017-03-22Cooling tower inspection — violation AH8C
2017-03-22Cooling tower inspection — violation AH8S
2017-03-22Cooling tower inspection — violation AH8A
2017-03-22Cooling tower inspection — violation AH8W
2017-03-22Cooling tower inspection — violation AH8B
2017-03-22Cooling tower inspection — violation AH8G
2017-03-22Cooling tower inspection — violation AH8H
2017-03-22Cooling tower inspection — violation AH8X
2017-03-22Cooling tower inspection — violation AH8D
2017-03-22Cooling tower inspection — violation AH8R
2017-03-22Cooling tower inspection — violation AH8S
2017-03-22Cooling tower inspection — violation AH8H
2017-03-22Cooling tower inspection — violation AH8U
2017-03-22Cooling tower inspection — violation AH8F
2017-03-22Cooling tower inspection — violation AH8V
2017-03-22Cooling tower inspection — violation AH8T
2017-03-22Cooling tower inspection — violation AH8T
2017-03-22Cooling tower inspection — violation AH8C
2017-03-22Cooling tower inspection — violation AH8L
2017-03-22Cooling tower inspection — violation AH9C
2017-03-22Cooling tower inspection — violation AH8E
2017-03-22Cooling tower inspection — violation AH8R
2017-03-22Cooling tower inspection — violation AH8Q
2017-03-20Job filed: INSTALL OF TEMPORARY PLATFORMS FOR UNIQLO GLOBAL PRESS EVENT SCHEDULED ON MARCH 29TH, 2017, NO ALTERATION OF EXISTING STRUCTURES, A TPA PERMIT IS REQU$5,000
2017-03-20Permit AL — ISSUED
2017-03-14311: Noise - Street/Sidewalk — Loud Talking
2017-02-27Certificate of occupancy Temporary
2017-02-07Job filed: INSTALL OF TEMPORARY PLATFORMS AND OTHER PRODUCTION EQUIPMENT FOR FASHION WEEK AT SPRING STUDIOS SCHEDULED ON FEBRUARY 11-15, 2017, NO ALTERATION OF E$5,000
2017-02-07Permit AL — ISSUED
2017-01-25Agreement — from COLUMN FINANCIAL, INC. to SPRING STUDIOS NEW YORK, LLC; 50 VARICK LLC
2017-01-25Agreement — from COLUMN FINANCIAL, INC. to SPRING STUDIOS NEW YORK, LLC; 50 VARICK LLC
2017-01-25AL&R $500,000,000 — from 50 VARICK LLC to COLUMN FINANCIAL, INC.$500,000,000
2017-01-25Agreement — from COLUMN FINANCIAL, INC. to SPRING STUDIOS NEW YORK, LLC; 50 VARICK LLC
2017-01-25Agreement — from COLUMN FINANCIAL, INC. to SPRING STUDIOS NEW YORK, LLC; 50 VARICK LLC
2017-01-25AL&R $500,000,000 — from 50 VARICK LLC to COLUMN FINANCIAL, INC.$500,000,000
2017-01-25Agreement — from COLUMN FINANCIAL, INC. to SPRING STUDIOS NEW YORK, LLC; 50 VARICK LLC
2017-01-25Agreement — from COLUMN FINANCIAL, INC. to SPRING STUDIOS NEW YORK, LLC; 50 VARICK LLC
2017-01-25Agreement — from COLUMN FINANCIAL, INC. to SPRING STUDIOS NEW YORK, LLC; 50 VARICK LLC
2017-01-25Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORMS FOR SPRING STUDIOS: GOLDMAN SACHS GLOBAL CONFERENCE SCHEDULED FOR FEB, 8, 9, 10 2017, NO ALTERATION OF EXISTIN$5,000
2017-01-25Job filed: INSTALL OF TEMPORARY INTERIOR PLATFORMS FOR SPRING STUDIOS: GOLDMAN SACHS GLOBAL CONFERENCE SCHEDULED FOR FEB, 8, 9, 10 2017, NO ALTERATION OF EXISTIN$5,000
2017-01-25Permit AL — ISSUED
2017-01-12Mortgage $500,000,000 — from ARC NY24549W17, LLC; ARC NY120W5701 TRS, LLC; ARC NY333W3401, LLC; 50 VARICK LLC; ARC NY22 to COLUMN FINANCIAL, INC.$500,000,000
2017-01-12Mortgage $500,000,000 — from ARC NY24549W17, LLC; ARC NY120W5701 TRS, LLC; ARC NY333W3401, LLC; 50 VARICK LLC; ARC NY22 to COLUMN FINANCIAL, INC.$500,000,000
2017-01-10Mortgage $51,358,894 — from 50 VARICK LLC to COLUMN FINANCIAL, INC.$51,358,894
2017-01-10Mortgage $51,358,894 — from 50 VARICK LLC to COLUMN FINANCIAL, INC.$51,358,894
2017-01-03DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2015 CAT 1 INSP/TST
2016
2016-12-06Certificate of occupancy Temporary
2016-12-02311: Illegal Parking — Double Parked Blocking Traffic
2016-11-30311: Traffic — Congestion/Gridlock
2016-11-30Permit AL — ISSUED
2016-11-28Job filed: INSTALLATION OF TEMP SEATING RISER FOR TARGET HOLIDAY BIG SHOW, LOC. AT 50 VARICK STREET , 6TH FLOOR, SCHED FOR DEC 7, 2016. A TEMPORARY PLACE OF ASSE$5,000
2016-11-28Job filed: INSTALLATION OF TEMP SEATING RISER FOR TARGET HOLIDAY BIG SHOW, LOC. AT 50 VARICK STREET , 6TH FLOOR, SCHED FOR DEC 7, 2016. A TEMPORARY PLACE OF ASSE$5,000
2016-11-28Job filed: INSTALLATION OF TEMP SEATING RISER FOR TARGET HOLIDAY BIG SHOW, LOC. AT 50 VARICK STREET , 6TH FLOOR, SCHED FOR DEC 7, 2016. A TEMPORARY PLACE OF ASSE$5,000
2016-11-14Job filed: INSTALL NEW SPRINKLER HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$201,350
2016-11-14Job filed: INSTALL NEW SPRINKLER HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$201,350
2016-11-10FDNY inspection (COMPLAINT)
2016-11-07Job filed: LOCAL LAW 26 COMPLIANCE. FILING TO INSTALL NEW FIRE SMOKE DAMPERS INTO EXISTING DUCTS AT VARIOUS LOCATIONS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHA$771,082
2016-11-07Job filed: HEREWITH FILING LOCAL LAW 26 COMPLIANCE. FILING FOR THE REMOVAL AND INSTALLATION OF NON-LOAD BEARING PARTITIONS, NEW FLOORING AND HUNG CEILING RELATED$959,582
2016-11-07Job filed: HEREWITH FILING LOCAL LAW 26 COMPLIANCE. FILING FOR THE REMOVAL AND INSTALLATION OF NON-LOAD BEARING PARTITIONS, NEW FLOORING AND HUNG CEILING RELATED$959,582
2016-11-03Job filed: INSTALLATION OF AUTOMATIC HEAT DETECTION FOR CFF-800 DUAL AGENT DELUG SUPPRESSION SYSTEM AS SHOWN ON DRAWINGS FILED HEREWITH.$300,000
2016-11-03Job filed: ADDITION MODIFICATION TO EXISTING FIRE ALARM SYSTEM$500,000
2016-11-03Job filed: INSTALLATION OF AUTOMATIC HEAT DETECTION FOR CFF-800 DUAL AGENT DELUG SUPPRESSION SYSTEM AS SHOWN ON DRAWINGS FILED HEREWITH.$300,000
2016-11-03Job filed: HEREWITH FILING FOR STRUCTURAL WORK FOR LOCAL LAW 26 COMPLIANCE AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$103,550
2016-11-03Job filed: ADDITION MODIFICATION TO EXISTING FIRE ALARM SYSTEM$500,000
2016-11-03Job filed: ADDITION TO THE EXISTING FIRE ALARM SYSTEM VESDA SMOKE DETECTORS AS SHOWN ON DRAWINGS FILED HEREWITH.$985,000
2016-11-03Job filed: ADDITION TO THE EXISTING FIRE ALARM SYSTEM VESDA SMOKE DETECTORS AS SHOWN ON DRAWINGS FILED HEREWITH.$985,000
2016-11-02Rodent inspection: Passed
2016-10-31FDNY inspection (COMPLAINT)
2016-10-26311: General Construction/Plumbing — Egress - Doors Locked/Blocked/Improper/No Secondary Means
2016-10-26DOB complaint, category ?
2016-10-19Job filed: INSTALLATION OF A TEMPORARY PLATFORM FOR THE PROJECT VOSTOK EVENT, LOCATED AT 50 VARICK STREET , 6TH FLOOR, SCHEDULED FOR OCTOBER 26TH, 2016. TPA IS R$5,000
2016-10-19Permit AL — ISSUED
2016-10-07Permit EW — ISSUED
2016-10-07Permit EW — ISSUED
2016-10-07Permit EW — ISSUED
2016-10-06311: Sewer — Catch Basin Clogged/Flooding (Use Comments) (SC)
2016-09-28Job filed: FILING FOR THE INSTALLATION OF STRUCTURAL STEEL DUNNAGE RELATED TO THE CABLE/DEHYDRATOR CHILLER INSTALLATION AS SHOWN ON DRAWINGS FILED HEREWITH. NO C$119,101
2016-09-28Job filed: FILING FOR THE INSTALLATION OF CABLE/DEHYDRATOR CHILLERS, RELATED PIPING AND MISCELLANEOUS GENERAL CONSTRUCTION WORK AS SHOWN ON DRAWINGS FILED HEREWI$655,147
2016-09-28Job filed: FILING FOR THE INSTALLATION OF CABLE/DEHYDRATOR CHILLERS, RELATED PIPING AND MISCELLANEOUS GENERAL CONSTRUCTION WORK AS SHOWN ON DRAWINGS FILED HEREWI$655,147
2016-09-26Job filed: INSTALLATION OF INTERIOR TEMPORARY PLATFORM FOR THE EVENT KNOWN AS GOOGLE THINK CONFERENCE SCHEDULED FOR SEPT 27, 2016. A TEMPORARY PLACE OF ASSEMBLY $5,000
2016-09-26Job filed: INSTALLATION OF INTERIOR TEMPORARY PLATFORM FOR THE EVENT KNOWN AS GOOGLE THINK CONFERENCE SCHEDULED FOR SEPT 27, 2016. A TEMPORARY PLACE OF ASSEMBLY $5,000
2016-09-26Permit AL — ISSUED
2016-09-19FDNY inspection (ALT)
2016-09-14Certificate of occupancy Temporary
2016-09-12FDNY inspection (ALT)
2016-08-24FDNY inspection (ALT)
2016-08-15Job filed: PA
2016-08-03Permit EW — ISSUED
2016-07-29Permit EW — ISSUED
2016-07-29Permit EW — ISSUED
2016-07-29Permit EW — ISSUED
2016-07-29Permit EW — ISSUED
2016-07-29Permit EW — ISSUED
2016-07-29Permit EW — ISSUED
2016-07-29Permit EW — ISSUED
2016-06-27FDNY inspection (RISK)
2016-06-21Certificate of occupancy Temporary
2016-06-14311: Sewer — Catch Basin Clogged/Flooding (Use Comments) (SC)
2016-05-06Job filed: PA
2016-05-04311: Noise - Street/Sidewalk — Loud Music/Party
2016-05-04311: Noise - Street/Sidewalk — Loud Talking
2016-04-26Permit AL — ISSUED
2016-04-25311: Noise - Street/Sidewalk — Loud Music/Party
2016-04-25311: Noise - Street/Sidewalk — Loud Music/Party
2016-04-25311: Noise - Street/Sidewalk — Loud Talking
2016-04-25Job filed: INSTALL INTERIOR PLATFORM SYSTEM & OTHER PRODUCTION EQUIPMENT FOR THE PRATT INSTITUTE FASHION RUNWAY SHOW EVENT, SCHEDULED FOR MAY 5TH, 2016. TPA $5,000
2016-04-14311: Noise - Street/Sidewalk — Loud Music/Party
2016-04-08Permit PL — ISSUED
2016-04-01Job filed: INSTALLATION OF AN INTERIOR PLATFORM SYSTEM FOR THE SHL CAPITAL BIRTHDAY EVENT, SCHEDULED FOR APRIL 9TH 2016. A TEMPORARY PLACE OF ASSEMBLY PERMIT IS $5,000
2016-04-01Permit AL — ISSUED
2016-03-31Job filed: INSTALL TEMPORARY INTERIOR PLATFORMS AND TRUSSING FOR THE TRIBECA FILM FESTIVAL EVENT AT SPRING STUDIOS, SCHEDULED FOR APRIL 10-25 2016. TPA IS REQUI$5,000
2016-03-31Permit AL — ISSUED
2016-03-29Certificate of occupancy Temporary
2016-03-22Permit EW — ISSUED
2016-03-21Permit EW — ISSUED
2016-03-21Permit EW — ISSUED
2016-03-18311: Indoor Sewage — Sewage Odor
2016-03-17Permit EW — RE-ISSUED
2016-03-15Permit AL — ISSUED
2016-03-15Permit EQ — ISSUED
2016-03-03DOB violation E:
2016-03-03DOB violation E:
2016-03-03DOB violation E:
2016-03-03DOB violation E:
2016-03-03DOB violation E:
2016-03-03DOB violation E:
2016-02-19Permit EW — ISSUED
2016-02-18Job filed: PA
2016-02-18Job filed: MINOR CONSTRUCTION WORK AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$60,000
2016-02-02Job filed: ADDITIONS/MODIFICATIONS TO THE EXISTING FIRE ALARM SYSTEM AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$9,500
2016-02-02Job filed: SPRINKLER MODIFICATIONS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$28,500
2016-01-21Permit EW — ISSUED
2016-01-21Permit EW — ISSUED
2016-01-20Job filed: MECHANICAL MODIFICATIONS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$30,000
2016-01-20Job filed: DEMOLISH AND CONSTRUCT INTERIOR PARTITIONS, CEILINGS AND DOORS IN CONJUNCTION WITH ALT 1 # 120911996 AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN$323,000
2016-01-20Job filed: MECHANICAL MODIFICATIONS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$30,000
2016-01-20Job filed: DEMOLISH AND CONSTRUCT INTERIOR PARTITIONS, CEILINGS AND DOORS IN CONJUNCTION WITH ALT 1 # 120911996 AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN$323,000
2015
2015-12-04Permit EW — ISSUED
2015-12-02Permit EW — ISSUED
2015-12-01Job filed: INSTALL PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$20,000
2015-12-01Job filed: CONSTRUCT INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$100,000
2015-11-16Certificate of occupancy Temporary
2015-11-10311: Taxi Complaint — Driver Complaint
2015-11-10Job filed: INSTALLATION OF KITCHEN FIRE SUPPRESSION SYSTEM IN CONJUNCTION WITH JOB#121813252. NO CHANGE IN USE, EGRESS OR OCCUPANCY.ALL COOKING EQPT ARE ELECTRIC$3,000
2015-10-29Job filed: INSTALLATION OF TEMPORARY INTERIOR PLATFORMS FOR THE EVENT KNOWN AS TRIBECA GAMES PRESENTS THE CRAFT & CREATIVE OF LEAGUE OF LEGENDS, SCHEDULED FO$5,000
2015-10-21Permit EW — RE-ISSUED
2015-09-21Permit PL — ISSUED
2015-09-11Permit EW — ISSUED
2015-09-11Permit EW — ISSUED
2015-09-11Permit EW — ISSUED
2015-09-10Permit PL — ISSUED
2015-09-02Job filed: DEMOLISH INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$6,000
2015-09-02Permit EW — ISSUED
2015-09-01Permit EW — ISSUED
2015-09-01Permit EW — ISSUED
2015-09-01Permit EW — ISSUED
2015-08-31Job filed: DEMOLISH AND CONSTRUCT INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$950,000
2015-08-31Job filed: MODIFICATION FIRE ALARM DEVICES TO THE EXISTING SYSTEM AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$28,000
2015-08-31Job filed: MODIFY MECHANICAL DUCTWORK ALONG WITH A/C UNIT. MODIFY PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGR$262,000
2015-08-31Job filed: MODIFICATION FIRE ALARM DEVICES TO THE EXISTING SYSTEM AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$28,000
2015-08-31Job filed: INSTALL NEW STEEL BEAM FRAMING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$10,000
2015-08-31Job filed: MODIFY SPRINKLER HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$90,000
2015-08-31Job filed: MODIFY MECHANICAL DUCTWORK ALONG WITH A/C UNIT. MODIFY PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGR$262,000
2015-08-31Job filed: INSTALL NEW STEEL BEAM FRAMING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$10,000
2015-08-31Job filed: DEMOLISH AND CONSTRUCT INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$950,000
2015-08-31Job filed: MODIFICATION FIRE ALARM DEVICES TO THE EXISTING SYSTEM AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$28,000
2015-08-20Certificate of occupancy Temporary
2015-08-19FDNY inspection (COMPLAINT)
2015-08-18311: Noise — Noise: air condition/ventilation equipment (NV1)
2015-06-14311: Graffiti — Graffiti
2015-05-27Certificate of occupancy Temporary
2015-05-23311: Sewer — Sewer Backup (Use Comments) (SA)
2015-04-17FDNY inspection (OTHER)
2015-04-10Job filed: INSTALLATION OF TEMPORARY INTERIOR PLARFORMS FOR THE EVENT KNOWN AS VEVO NEWFRONT, SCHEDULED FOR APRIL 30TH 2015. A TEMPORARY PLACE OF ASSEMBLY PERMIT$5,000
2015-04-10Permit AL — ISSUED
2015-04-02Permit AL — ISSUED
2015-04-01Job filed: INSTALLATION OF INTERIOR TEMPORARY PLATFORMS AND TRUSSES FOR THE EVENT KNOWN AS TRIBECA FILM FESTIVAL, SCHEDULED FOR APRIL 14TH 2015. A TEMPORARY PLAC$5,000
2015-04-01Job filed: INSTALLATION OF INTERIOR TEMPORARY PLATFORMS AND TRUSSES FOR THE EVENT KNOWN AS TRIBECA FILM FESTIVAL, SCHEDULED FOR APRIL 14TH 2015. A TEMPORARY PLAC$5,000
2015-03-23Permit EW — ISSUED
2015-03-23Permit EW — ISSUED
2015-03-23Permit EW — ISSUED
2015-03-23Permit EW — ISSUED
2015-03-23Permit EW — ISSUED
2015-03-03DOB violation E:
2015-03-03DOB violation E:
2015-03-03DOB violation E:
2015-03-03DOB violation E:
2015-03-03DOB violation E:
2015-03-03DOB violation E:
2015-02-10Certificate of occupancy Temporary
2015-01-28Permit EW — ISSUED
2014
2014-11-17Certificate of occupancy Temporary
2014-10-24FDNY inspection (FORTH)
2014-10-20FDNY inspection (FORTH)
2014-10-09311: Noise — Noise: Construction Before/After Hours (NM1)
2014-10-09Job filed: INSTALLATION OF TEMPORARY INTERIOR SEATING PLATFORMS AND OTHER PRODUCTION EQUIPMENT, FOR THE EVENT KNOWN AS NIKE WGML, SCHEDULED FOR OCTOBER 21-23 201$5,000
2014-10-09Permit AL — ISSUED
2014-10-07Permit EW — ISSUED
2014-10-07Permit EW — ISSUED
2014-09-30Permit AL — ISSUED
2014-09-22Job filed: INSTALLATION OF TEMPORARY INTERIOR TRUSSING AND INTERIOR PLATFORMS FOR THE EVENT KNOWN AS, THINK BRAND WITH GOOGLE, LOCATED INTERIOR OF SPRING STUDIOS$5,000
2014-09-22Permit AL — ISSUED
2014-08-25Certificate of occupancy Temporary
2014-08-15ECB CLASS - 2 violation: 100R10-REMOVE TEMP WALL IN HOISTWAY BETWEEN CARS.$2,500
2014-08-14Job filed: FILING HEREWITH FIRE PROTECTION PLAN AS SHOWN ON DRAWINGS FILED HEREWITH. IN CONJUNCTION WITH ALT I#120911996$1,000
2014-07-22ECB CLASS - 2 violation: 34L10,64M07,70O02,34O02,100B07,05X10. 34L10-HOISTWAY ACCESS SWITCHES NOT WORKING; 64M07-NYC DEVICE #TOP OF CAR MISSING; 70O02-CLEA$2,500
2014-07-22ECB CLASS - 2 violation: 97R07,39R09. 97R07-ILLEGAL OPERATION OF DEVICE 1P4637 OPERATING W/O CERTIFICATE OF COMPLIANCE. 6TH FLR REAR AND 7TH FLR REAR ENT$2,500
2014-07-22ECB CLASS - 2 violation: 97R07,39R09. 97R07-AN ILLEGAL OPERATION OF DEVICE #1P6493 OPERATING W/O CERTIFICATE OF COMPLIANCE. 6TH FLR REAR AND 7TH FLOOR REAR$2,500
2014-07-22ECB CLASS - 2 violation: 34L10,64N07,70O02,34O02,100B07,05X10. 34L10-HOISTWAY ACCESS SWITCHES NOT WORKING; 64M07-NYC SWITCH TOP OF CAR MISSING; 70O02-CLEAN$2,500
2014-07-21ECB CLASS - 2 violation: 41B07,39B07,42N09,70O02,64M07,100#10. 41B07-PROVIDE MOTOR ROOM DOOR TOCODE (MADE OF PLYWOOD); 39B07-PROVIDE A SAFE AND ACCESSIBLE
2014-07-21ECB CLASS - 2 violation: 100L10,64M07,70O02. 100L10-CAR BYPASS/ACCESS SWITCHES NOT WORKING REPAIR; 64M07-NYC DEVICE AND TOP OF CAR MISSING PROVIDE; 70O02-C
2014-07-16Permit EW — ISSUED
2014-07-09Job filed: INSTALLATION OF AUTOMATIC HEAT DETECTION SYSTEM FOR PRE ACTION SPRINKLER SYSTE M AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCC$3,000
2014-07-09Job filed: INSTALLATION OF AUTOMATIC HEAT DETECTION SYSTEM FOR PRE ACTION SPRINKLER SYSTE M AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCC$3,000
2014-06-24Permit AL — RE-ISSUED
2014-06-24Permit EQ — ISSUED
2014-06-03311: Street Light Condition — Street Light Out
2014-05-30DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2012 CAT 1 INSP/TST
2014-05-30DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2012 CAT 1 INSP/TST
2014-05-30DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2012 CAT 1 INSP/TST
2014-05-30DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2012 CAT 1 INSP/TST
2014-05-30DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2012 CAT 1 INSP/TST
2014-05-30DOB violation ACC1: VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2012 CAT 1 INSP/TST
2014-04-02Permit EQ — ISSUED
2014-03-21Permit EW — ISSUED
2014-03-21Permit AL — RE-ISSUED
2014-03-21Permit EQ — ISSUED
2014-03-21Permit EW — ISSUED
2014-03-21Permit EW — ISSUED
2014-03-20Job filed: INSTALLATION OF HEAVY DUTY SIDEWALK SHED FOR REMEDIAL REPAIRS. LIVE LOAD 300 PSF. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE 2008 CODE NO CHAN
2014-03-20Permit EQ — ISSUED
2014-03-07SAGE — from THOR 50 VARICK BRIDGE LENDER LLC
2014-03-06DOB violation E:
2014-03-06DOB violation E:
2014-03-06DOB violation E:
2014-03-06DOB violation E:
2014-03-06DOB violation E:
2014-03-06DOB violation E:
2014-03-05FDNY inspection (ABATE)
2014-02-11311: Building/Use — No Certificate Of Occupancy/Illegal/Contrary To CO
2014-02-11DOB complaint, category ?
2014-01-31Permit EW — ISSUED
2014-01-29Permit EQ — ISSUED
2014-01-29Permit AL — ISSUED
2014-01-20311: Street Condition — Defective Hardware
2014-01-15Job filed: CONSTRUCTION OF BULKHEAD AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$200,000
2014-01-15Job filed: STRUCTURAL WORK FOR BULKHEAD AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$940,000
2014-01-15Job filed: MODIFICATION OF THE EXISTING FIRE ALARM SYSTEM AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$5,000
2014-01-15Job filed: STRUCTURAL WORK FOR BULKHEAD AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$940,000
2014-01-14ECB CLASS - 2 violation: 97X10 - RETURN TO SERVICE.
2014-01-14ECB CLASS - 2 violation: 02X10 - 2WAY COMMUNICATION INOPERABLE.
2014-01-14ECB CLASS - 2 violation: 02X10-2WAY COMMUNICATION INOPERABLE.
2014-01-14ECB CLASS - 2 violation: 02X10,40M07. 02X10-2WAY COMMUNICATION-INOPERABLE; 40M-PROVIDE SAFE ANDSECURE LADDER LEADING TO MACHINE ROOM.
2014-01-14ECB CLASS - 2 violation: 21B01,40M07,60X10,64B07. 40M-PROVIDE SAFE AND SECURE LADDER LEADING TOMACHINE ROOM; 64B-PROVIDE CORRECT NYC ID#ON CONSTRUCTION; 21
2014-01-13Permit PL — ISSUED
2013
2013-12-05DOB violation E:
2013-12-05DOB violation E:
2013-12-05DOB violation E:
2013-12-05DOB violation E:
2013-12-05DOB violation E:
2013-12-05DOB violation E:
2013-11-12Permit PL — ISSUED
2013-11-11311: Noise - Commercial — Loud Music/Party
2013-10-30Permit EW — ISSUED
2013-10-30Permit EW — ISSUED
2013-10-30Permit EW — ISSUED
2013-10-17Job filed: MODIFY STRUCTURAL WORK AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$80,000
2013-10-17Job filed: MODIFY MECHANICAL DUCTWORK. MODIFY PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$350,000
2013-10-17Job filed: DEMOLISH AND CONSTRUCT INTERIOR PARTITIONS, CEILINGS & DOORS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$1,930,000
2013-10-17Job filed: MODIFY MECHANICAL DUCTWORK. MODIFY PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$350,000
2013-10-17Job filed: MODIFICATION FIRE ALARM SYSTEM TO THE EXISTING SYSTEM AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$41,000
2013-10-17Job filed: MODIFY SPRINKLER HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$1,186,600
2013-10-09FDNY inspection (ABATE)
2013-10-02311: Street Light Condition — Street Light Out
2013-10-02DOB complaint, category ?
2013-09-07311: Noise — Noise: Construction Equipment (NC1)
2013-09-06FDNY inspection (SPECIAL-OTH)
2013-09-05Permit AL — ISSUED
2013-09-05Permit EQ — ISSUED
2013-08-19Mortgage satisfied — from 50 VARICK LLC to MEDIOCREDITO ITALIANO, S.P.A.
2013-08-19Mortgage satisfied — from 50 VARICK LLC to MEDIOCREDITO ITALIANO, S.P.A.
2013-08-16FDNY inspection (ABATE)
2013-07-23RPTT&RET $72,000,000 — from CRIVELLI, GIORGIO CAJRATI; HAWKSFORD TRUSTEES JERSEY LTD AS TRUSTEE; TAZARTES, ANTONIO; SI to AMERICAN REALTY CAPITAL NEW YORK RECOVER$72,000,000
2013-07-23RPTT&RET $72,000,000 — from CRIVELLI, GIORGIO CAJRATI; HAWKSFORD TRUSTEES JERSEY LTD AS TRUSTEE; TAZARTES, ANTONIO; SI to AMERICAN REALTY CAPITAL NEW YORK RECOVER$72,000,000
2013-07-16SAGE — from 50 VARICK LLC; THOR 50 VARICK BRIDGE LENDER LLC
2013-07-12FDNY inspection (ABATE)
2013-06-29311: Noise — Noise: air condition/ventilation equipment (NV1)
2013-06-27Permit EW — ISSUED
2013-06-15311: Noise — Noise: Construction Before/After Hours (NM1)
2013-06-12Permit AL — ISSUED
2013-06-12Permit EQ — ISSUED
2013-06-03DOB violation BENCH: FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4
2013-05-25311: Derelict Vehicles — Derelict Vehicles
2013-05-08FDNY inspection (ABATE)
2013-04-29FDNY inspection (COMPLAINT)
2013-04-13311: Noise — Noise: Construction Before/After Hours (NM1)
2013-04-04Permit EQ — ISSUED
2013-04-01Permit EQ — ISSUED
2013-04-01Permit EQ — ISSUED
2013-03-28311: Emergency Response Team (ERT) — After Hours Work - Illegal
2013-03-28DOB complaint, category ?
2013-02-20Rodent inspection: Passed
2013-02-15Facade (LL11) filing, cycle 7: SWARMP
2013-02-01311: Water System — No Water/Low Pressure (WA5)
2013-01-17Permit PL — ISSUED
2012
2012-12-29311: Noise — Noise: Construction Before/After Hours (NM1)
2012-12-20311: Found Property — Electronics/Phones
2012-11-28CORRD — from VERIZON NEW YORK INC. to 50 VARICK LLC
2012-11-21Deed $286,051 — from VERIZON NEW YORK INC. to 50 VARICK LLC$286,051
2012-11-07Permit EW — ISSUED
2012-10-24ADEC — from 50 VARICK STREET CONDOMINIUM
2012-10-24ADEC — from 50 VARICK STREET CONDOMINIUM
2012-10-24ADEC — from 50 VARICK STREET CONDOMINIUM
2012-10-24MAPS — from 50 VARICK STREET CONDOMINIUM
2012-10-24MAPS — from 50 VARICK STREET CONDOMINIUM
2012-10-24MAPS — from 50 VARICK STREET CONDOMINIUM
2012-10-24MAPS — from 50 VARICK STREET CONDOMINIUM
2012-10-24ADEC — from 50 VARICK STREET CONDOMINIUM
2012-10-24MAPS — from 50 VARICK STREET CONDOMINIUM
2012-10-24ADEC — from 50 VARICK STREET CONDOMINIUM
2012-10-24ADEC — from 50 VARICK STREET CONDOMINIUM
2012-10-24ADEC — from 50 VARICK STREET CONDOMINIUM
2012-10-24MAPS — from 50 VARICK STREET CONDOMINIUM
2012-10-24MAPS — from 50 VARICK STREET CONDOMINIUM
2012-10-01311: Air Quality — Air: Dust, Construction/Demolition (AE4)
2012-08-08Permit EW — ISSUED
2012-08-07Permit EW — ISSUED
2012-08-03Permit EW — ISSUED
2012-08-03Permit EW — ISSUED
2012-08-03Permit EW — ISSUED
2012-07-24311: Noise — Noise: air condition/ventilation equipment (NV1)
2012-07-17Permit EW — ISSUED
2012-07-17Permit EW — ISSUED
2012-07-17Permit EW — ISSUED
2012-07-17Permit EW — ISSUED
2012-06-28Permit EQ — ISSUED
2012-06-27Job filed: INSTALLATION OF INTERIOR SCAFFOLD @ 7TH FLOOR AS PER PLANS DURING STRUCTURAL WORK (FILED SEPARATELY). NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD
2012-06-27Job filed: INSTALLATION OF INTERIOR SCAFFOLD @ 7TH FLOOR AS PER PLANS DURING STRUCTURAL WORK (FILED SEPARATELY). NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD
2012-06-19Agreement — from BOARD OF MANAGERS OF 50 VARICK STREET CO to SPRING STUDIOS NEW YORK, LLC
2012-06-12Permit AL — ISSUED
2012-06-12Permit EQ — ISSUED
2012-05-17311: Noise — Noise: Construction Equipment (NC1)
2012-05-06311: General Construction/Plumbing — Sidewalk Shed/Pipe Scafford - Inadequate Defective/None
2012-05-06DOB complaint, category ?
2012-05-03DOB violation BENCH: FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4
2012-04-28311: Noise — Noise: Construction Equipment (NC1)
2012-04-21311: Noise — Noise: Construction Equipment (NC1)
2012-04-12Agreement — from MEDIOCREDITO ITALANO S.P.A. to SPRING STUDIOS NEW YORK LLC
2012-04-04311: General Construction/Plumbing — Sidewalk Shed/Pipe Scafford - Inadequate Defective/None
2012-04-04DOB complaint, category ?
2012-03-29Permit EQ — ISSUED
2012-03-29Permit EQ — ISSUED
2012-03-29Permit EQ — ISSUED
2012-03-28Permit AL — ISSUED
2012-03-28Permit EQ — ISSUED
2012-03-27Job filed: FIRE ALARM ADDITIONS TO THE EXISTING MODIFIED CLASS E FIRE ALARM SYSTEM. THERE IS NOT CHANGE IN USE, EGRESS, AND OR OCCUPANCY FILED UNDER THIS APPLICA$54,000
2012-03-27Job filed: FIRE ALARM ADDITIONS TO THE EXISTING MODIFIED CLASS E FIRE ALARM SYSTEM.$54,000
2012-03-23Job filed: INSTALLATION OF FENCE AS PER PLANS. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION. FENCE SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2008
2012-03-23Job filed: INSTALLATION OF HEAVYDUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH C
2012-03-23Job filed: INSTALLATION OF HEAVYDUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION. SIDEWALK SHED SHALL COMPLY WITH C
2012-03-23Job filed: INSTALLATION OF FENCE AS PER PLANS. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION. FENCE SHALL COMPLY WITH CHAPTER 33 OF THE NYC 2008
2012-03-23Job filed: INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER 33
2012-03-16Rodent inspection: Passed
2012-03-06ADEC — from 50 VARICK STREET CONDOMINIUM
2012-03-06ADEC — from 50 VARICK STREET CONDOMINIUM
2012-03-06ADEC — from 50 VARICK STREET CONDOMINIUM
2012-03-06MAPS — from 50 VARICK STREET CONDOMINIUM
2012-03-06ADEC — from 50 VARICK STREET CONDOMINIUM
2012-03-06MAPS — from 50 VARICK STREET CONDOMINIUM
2012-03-06MAPS — from 50 VARICK STREET CONDOMINIUM
2012-03-06MAPS — from 50 VARICK STREET CONDOMINIUM
2012-03-06MAPS — from 50 VARICK STREET CONDOMINIUM
2012-03-06MAPS — from 50 VARICK STREET CONDOMINIUM
2012-03-06ADEC — from 50 VARICK STREET CONDOMINIUM
2012-03-06ADEC — from 50 VARICK STREET CONDOMINIUM
2012-01-19Permit PL — ISSUED
2012-01-03Permit EW — ISSUED
2012-01-03Permit EW — ISSUED
2012-01-03Permit EW — ISSUED
2012-01-01DOB violation BENCH: FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4
2011
2011-12-15311: Electrical — Electrical Wiring Defective/Exposed
2011-12-15DOB complaint, category ?
2011-12-13311: Noise — Noise: Construction Before/After Hours (NM1)
2011-12-13Job filed: PROPOSE TO REMOVE & INSTALL NEW SPRINKLER HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCHY. IN$1,084,300
2011-12-13Job filed: MODIFICATION OF THE EXISTING FIRE ALARM SYSTEM AS SHOWN ON DRAWNGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. IN CONJUNCTION WITH ALT I#$115,000
2011-12-13DOB violation EVCAT1: VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2010 INSPECTION/TEST
2011-12-12Job filed: PROPOSE TO INSTALL MECHANICAL DUCTWORK, FANS AND UNITS. REMOVE, REPLACE, RELOCATE AND INSTALL NEW FIXTURES AND PIPING AS SHOWN ON DRAWINGS FILED HERE
2011-12-12Job filed: PROPOSE TO INSTALL STRUCTURAL STEEL FRAMING AS SHOWN ON DRAWINGS FILED HEREWITH.
2011-12-12Job filed: PROPOSE TO INSTALL MECHANICAL DUCTWORK, FANS AND UNITS. REMOVE, REPLACE, RELOCATE AND INSTALL NEW FIXTURES AND PIPING AS SHOWN ON DRAWINGS FILED HERE
2011-12-06311: Noise — Noise: Construction Equipment (NC1)
2011-12-01311: Asbestos — Asbestos Complaint (B1)
2011-11-30Job filed: A1$9,716,894
2011-11-16311: Noise — Noise: Construction Equipment (NC1)
2011-11-03Job filed: DEMOLISH INTERIOR PARTITIONS, CEILINGS, DOORS & FLOORS. REMOVE PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHAN$90,000
2011-11-03Job filed: DEMOLISH INTERIOR PARTITIONS, CEILINGS, DOORS & FLOORS. REMOVE PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHAN$90,000
2011-11-03Permit EW — ISSUED
2011-10-27Permit EW — ISSUED
2011-10-26Permit EW — ISSUED
2011-10-26Permit EW — RE-ISSUED
2011-10-26Permit EW — ISSUED
2011-10-20Permit EW — ISSUED
2011-10-20Permit EW — ISSUED
2011-10-20Permit EW — ISSUED
2011-08-08Mortgage $20,000,000 — from 50 VARICK LLC to MEDIOCREDITO ITALIANO S.P.A.$20,000,000
2011-06-06Permit EW — ISSUED
2011-06-06Permit EW — ISSUED
2011-05-21311: Cranes and Derricks — Crane/Suspension Scaffold - No Permit/License/Cert./Unsafe/Illegal
2011-05-21DOB complaint, category ?
2011-05-10Permit EW — ISSUED
2011-05-10Permit EW — ISSUED
2011-05-04Job filed: FILING FOR THE MODIFICATIONS OF THE EXISTING FIRE ALARM SYSTEM AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$12,000
2011-05-02Job filed: PROPOSE TO REINFORCE BARS STRUCTURAL WORK AS SHOWN ON DRAWINGS FILED HEREWITH AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPAN$766,080
2011-05-02Job filed: FILING FOR MINOR NON-LOAD BEARING PARTITION CHANGES, DOOR CHANGES AND MISCELLANEOUS GENERAL CONSTRUCTION WORK AS SHOWN ON DRAWINGS FILED HEREWITH. NO$550,000
2011-05-02Job filed: FILING FOR MECHANICAL WORK AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$30,000
2011-05-02Job filed: PROPOSE TO REINFORCE BARS STRUCTURAL WORK AS SHOWN ON DRAWINGS FILED HEREWITH AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPAN$766,080
2011-05-02Job filed: REMOVAL OF ROOF PARAPET; GRAVEL, ROOFING MEMBRANE AS SHOWN ON DRAWINGS FILED HEREWITH AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR$608,832
2011-03-21Rodent inspection: Passed
2011-02-14311: Street Condition — Defective Hardware
2011-02-07Rodent inspection: Failed for Rat Activity
2011-01-25Job filed: REMOVE OF FA DEVICES FROM THE EXSTG FA SYSTEM TROUGHOUT 7TH FLR TO ACCOMMODATE FLR RENO AS SHOWN ON DWGS FILED HEREWITH. NO CHANGE TO USE EGRESS OR OC$90,000
2011-01-25Job filed: REMOVE FIRE ALARM DEVICES TO THE EXISTING FA SYSTEM THROUGHOUT 6TH FL TO ACCOM MODATE FLR RENO AS SHOWN ON DWGS FILED HEREWITH. NO CHANGE IN USE, EGRE$90,000
2011-01-25Job filed: REMOVE FIRE ALARM DEVICES TO THE EXISTING FA SYSTEM THROUGHOUT 6TH FL TO ACCOM MODATE FLR RENO AS SHOWN ON DWGS FILED HEREWITH. NO CHANGE IN USE, EGRE$90,000
2011-01-25Job filed: REMOVE OF FA DEVICES FROM THE EXSTG FA SYSTEM TROUGHOUT 7TH FLR TO ACCOMMODATE FLR RENO AS SHOWN ON DWGS FILED HEREWITH. NO CHANGE TO USE EGRESS OR OC$90,000
2011-01-25Job filed: REMOVE FIRE ALARM DEVICES TO THE EXISTING FA SYSTEM THROUGHOUT 6TH FL TO ACCOM MODATE FLR RENO AS SHOWN ON DWGS FILED HEREWITH. NO CHANGE IN USE, EGRE$90,000
2011-01-19Permit EW — ISSUED
2011-01-14Permit EW — ISSUED
2011-01-13Permit PL — ISSUED
2011-01-04Permit EW — ISSUED
2011-01-04Permit EW — ISSUED
2011-01-04Permit EW — ISSUED
2011-01-04Permit EW — ISSUED
2011-01-04Permit EW — RE-ISSUED
2010
2010-12-28Permit EW — ISSUED
2010-12-28Permit EW — ISSUED
2010-12-28Permit EW — ISSUED
2010-12-28Permit EW — ISSUED
2010-12-22Permit EW — ISSUED
2010-12-22Permit EW — ISSUED
2010-12-22Permit EW — ISSUED
2010-12-15Job filed: PROPOSE TO DEMOLISH AND CONSTRUCT INTERIOR PARTITIONS, CEILINGS AND DOORS ON 1ST FLOOR AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS O$475,000
2010-12-15Job filed: MODIFY MECHANICAL DUCTWORK . MODIFY PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$216,000
2010-12-15Job filed: MODIFY MECHANICAL DUCTWORK . MODIFY PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$216,000
2010-12-15Job filed: MODIFY MECHANICAL DUCTWORK. PROPOSE TO MODIFY THE PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS $111,000
2010-12-15Job filed: DEMOLISH AND CONSTRUCT INTERIOR PARTITIONS, CEILINGS AND DOORS ON 6TH FLOOR AS SHOWN ON DRAWINGS FILED HEREWITH AS SHOWN ON DRAWINGS FILED HEREWITH. N$1,382,000
2010-12-15Job filed: DEMOLISH AND CONSTRUCT INTERIOR PARTITIONS, CEILINGS AND DOORS ON 6TH FLOOR AS SHOWN ON DRAWINGS FILED HEREWITH AS SHOWN ON DRAWINGS FILED HEREWITH. N$1,382,000
2010-11-30Permit PL — ISSUED
2010-11-18Permit EW — ISSUED
2010-11-17Permit EW — ISSUED
2010-11-17Permit EW — ISSUED
2010-11-12311: Emergency Response Team (ERT) — After Hours Work - Illegal
2010-11-12DOB violation E:
2010-11-12DOB violation E:
2010-11-12DOB violation E:
2010-11-12DOB violation E:
2010-11-12DOB violation E:
2010-11-12DOB complaint, category ?
2010-11-12DOB violation E:
2010-10-13Permit EW — RE-ISSUED
2010-09-29Permit EW — ISSUED
2010-09-23Permit EW — ISSUED
2010-08-26Job filed: .$35,000
2010-08-26Job filed: FILING FOR ADDITIONS/MODIFICATIONS TO CLASS 'E' FIRE ALARM SYSTEM AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$75,000
2010-08-26Job filed: .$35,000
2010-08-26Job filed: FILING FOR AUTOMATIC SMOKE DETECTION SYSTEM (VESDA) ON 2ND FL AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$15,000
2010-08-24Job filed: FILING FOR THE REMOVAL AND INSTALLATION OF MECHANICAL EQUIPMENT AND RELATED DUCTWORK AND PLUMBING WORK AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE $591,000
2010-08-24Job filed: FILING FOR PARTITION CHANGES, NEW FLOORING AND HUNG CEILING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$480,000
2010-08-24Job filed: FILING FOR THE REMOVAL AND INSTALLATION OF MECHANICAL EQUIPMENT AND RELATED DUCTWORK AND PLUMBING WORK AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE $591,000
2010-08-24Job filed: FILING FOR PARTITION CHANGES, NEW FLOORING AND HUNG CEILING AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$480,000
2010-08-24Job filed: FILING FOR STRUCTURAL WORK AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$25,000
2010-08-24Job filed: FILING FOR STRUCTURAL WORK AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$40,000
2010-08-24Job filed: FILING FOR THE INSTALLATION AND MODIFICATION OF MECHANICAL EQUIPMENT AND PLUMBING WORK AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS O$343,000
2010-08-24Job filed: A2$602,000
2010-08-19Job filed: FILING FOR SPRINKLER AND TO REPLACE (2) FIRE PUMPS (STANDPIPE) . ALL WORK AS S HOWN ON DRAWING FILED HEREWITH NO CHANGE IN USE EGRESS OR OCCUPANCY$471,300
2010-08-18Permit EW — ISSUED
2010-08-18Permit EW — ISSUED
2010-05-06Job filed: FILING FOR THE REMOVAL AND INSTALLATION OF PARTITIONS, FLOORING AND CEILINGS RELATED TO THE REMOVAL OF AN ESCALATOR AS SHOWN ON DRAWINGS FILED HEREWIT$100,000
2010-05-06Job filed: FILING FOR FLOOR FRAMING AND INFILL ON THE 5TH AND 6TH FLOOR IN RELATION TO THE REMOVAL OF AN ESCALATOR AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE$60,000
2010-05-06Job filed: FILING FOR THE REMOVAL AND INSTALLATION OF PARTITIONS, FLOORING AND CEILINGS RELATED TO THE REMOVAL OF AN ESCALATOR AS SHOWN ON DRAWINGS FILED HEREWIT$100,000
2010-05-06Job filed: FILING FOR FLOOR FRAMING AND INFILL ON THE 5TH AND 6TH FLOOR IN RELATION TO THE REMOVAL OF AN ESCALATOR AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE$60,000
2010-04-20311: Noise — Noise: Air Condition/Ventilation Equip, Residential (NJ1)
2010-04-08PAT — from 50 VARICK LLC to BOARD OF MAMAGERS
2010-04-08Deed $12,000,000 — from VERIZON NEW YORK INC. to 50 VARICK LLC$12,000,000
2010-04-08Agreement — from MEDIOCREDITO ITALIANO S.P.A., to VERIZON CORPORATE REAL ESTATE
2010-04-08PAT — from VERIZON NEW YORK INC., to BOARD OF MAMAGERS
2010-04-08PAT — from VERIZON NEW YORK INC., to BOARD OF MAMAGERS
2010-04-08PAT — from VERIZON NEW YORK INC., to BOARD OF MAMAGERS
2010-04-08PAT — from VERIZON NEW YORK INC., to BOARD OF MAMAGERS
2010-04-08PAT — from VERIZON NEW YORK INC., to BOARD OF MAMAGERS
2010-04-08Mortgage $7,800,000 — from 50 VARICK LLC to MEDIOCREDITO ITALIANO S.P.A.,$7,800,000
2010-03-12CDEC — from 50 VARICK STREET CONDOMINIUM
2010-03-12CDEC — from 50 VARICK STREET CONDOMINIUM
2010-03-12MAPS — from 50 VARICK STREET CONDOMINIUM
2010-03-12CDEC — from 50 VARICK STREET CONDOMINIUM
2010-03-12CDEC — from 50 VARICK STREET CONDOMINIUM
2010-03-12CDEC — from 50 VARICK STREET CONDOMINIUM
2010-03-12MAPS — from 50 VARICK STREET CONDOMINIUM
2010-03-12MAPS — from 50 VARICK STREET CONDOMINIUM
2010-03-12CDEC — from 50 VARICK STREET CONDOMINIUM
2010-03-12MAPS — from 50 VARICK STREET CONDOMINIUM
2010-03-12MAPS — from 50 VARICK STREET CONDOMINIUM
2010-03-12MAPS — from 50 VARICK STREET CONDOMINIUM
2010-03-08Job filed: FILING HEREWITH CONDOMINIUM SUBDIVISION APPLICATION. BLOCK: 212 LOT: 9 CONDOMINIUM LOTS: 1301 TO 1306.
2010-03-08Job filed: FILING HEREWITH CONDOMINIUM SUBDIVISION APPLICATION. BLOCK: 212 LOT: 9 CONDOMINIUM LOTS: 1301 TO 1306.
2010-02-26DOB violation E:
2010-02-26DOB violation E:
2010-02-10Job filed: FILING HEREWITH CONDOMINIUM SUBDIVISION APPLICATION. BLOCK: 212 LOT: 9 CONDOMINIUM LOTS: 1101 TO 1106.
2010-02-10Job filed: FILING HEREWITH CONDOMINIUM SUBDIVISION APPLICATION. BLOCK: 212 LOT: 9 CONDOMINIUM LOTS: 1101 TO 1106.
2010-01-19Rodent inspection: Passed
2009
2009-03-25DOB violation E:
2009-03-25DOB violation E:
2009-03-25DOB violation E:
2009-03-25DOB violation E:
2008
2008-06-03Permit EW — ISSUED
2008-05-30Job filed: REPLACEMENT OF EXISTING AIR CONDITIONING UNIT ON THE ROOF. NO CHANGE IN USE EGRESS OR OCCUPANCY.$40,000
2008-04-15DOB violation E:
2008-04-15DOB violation E:
2008-04-15DOB violation E:
2008-04-15DOB violation E:
2008-04-15DOB violation E:
2008-04-15DOB violation E:
2007
2007-10-03Permit EW — ISSUED
2007-10-03Permit EW — ISSUED
2007-09-24Job filed: FILING FOR DUCTWORK CHANGES AND MECHANICAL WORK AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$50,000
2007-09-24Job filed: FILING FOR MINOR PARTITION CHANGES AND MISCELLANEOUS GENERAL CONSTRUCTION WORK RELATED TO THE EQUIPMENT ROOM BUILD-OUT AS SHOWN ON DRAWINGS FILED HERE$50,000
2007-09-24Job filed: FILING FOR MODIFICATION TO THE EXISTINGFIRE ALARM SSYTEM AS SHOWN ON DR AWING FILED HEREWITH. NO CHANGE IN USE,EGRESS OR OCCUPANCY.$10,000
2007-09-06DOB complaint, category ?
2007-09-06DOB complaint, category ?
2007-09-06ECB Hazardous violation: WORK W/O A PERMIT. DURING INSPECTION ALTERATION HAS STARTED @ 3RD FLR.NORTH-WING FOR ADDITIONAL OFFICE SPACE. METAL STUDS HAVE BEE$2,500
2007-07-12Permit EW — ISSUED
2007-04-30ECB Non-Hazardous violation: 57H10/.57-H-10-REPAIR MOTOR BEARING(MACHINE)$180
2007-03-07Job filed: Filing To Create A Record Of LL5/73 Compliance - No Work To Be Performed Under This Application. See Commments Section 16- Including Ai1- additional I$100
2007-03-02Permit EW — ISSUED
2006
2006-10-30Job filed: FILLING HEREWITH TO RECORD COMPARTMENTATION ARRANGEMENT IN ACCORDANCE WI TH LOCAL LAW 5/73. AL RELATED WORK WAS FILED UNDER A SEPERATE APPLIC.10354209$1,000
2006-10-16Facade (LL11) filing, cycle 6: SAFE
2006-08-31DOB violation E:
2006-08-31DOB violation E:
2006-08-08ECB Non-Hazardous violation: 41B09,85BB05,83X10. (41) REMOVE BLOCKS FROM HG & EX RELAY. (85) EXPIRED 5 YRS TEST TAG; PERFORM & FILE TEST. (83) RESTORE TO SERVI$350
2006-08-08ECB Non-Hazardous violation: 85BB05,41A10. (85) EXPIRED 5 YR TEST TAG; PERFORM & FILE TEST. (41) JUMPERS ON STUD BLOCK; REMOVE JUMP FROM BOARD; REPAIR PROBLEM.$350
2006-08-01ECB Non-Hazardous violation: 83-R-#/83-ENTIRE DEVICE REMOVED W/O PERMIT FROM DOB.REMEDY:FILE & OBTAIN PERMIT
2006-08-01ECB Non-Hazardous violation: 83-X-10/86-M-05/83-RETURN TO SERVICE FOR PROPER INSPECTION OR FILE FOR REMOVAL OF DEVICE/86-NO TEO YEAR TEST PERFORM & FILE TEST$2,500
2006-08-01ECB Non-Hazardous violation: 83-X-10/86-M-05/83-RETURN TO SERVICE FOR PROPER INSPECION OR FILE FOR REMOVAL OF DEVICE/86-NO TWO YEAR PERFORM & FILE TEST$2,500
2006-08-01ECB Non-Hazardous violation: 83-R-#/83-ENTIRE DEVICE REMOVED W/O PERMIT FILE & OBTAIN PERMIT FROM DOB
2006-07-24Permit EQ — RE-ISSUED
2006-04-28Permit EW — ISSUED
2006-04-19Job filed: Filing for facade repairs as shown on drawings filed herewith. No change in use, egress or occupancy.$60,000
2006-04-06Job filed: PROPOSED INSTALLATION OF 55 LINEAR FEET OF HEAVY DUTY SIDEWALK SHED FOR REMEDIAL REPAIRS. SIDEWALK SHED SHALL COMPLY WITH LL 33/91. NO CHANGE IN USE,
2006-04-06Job filed: PROPOSED INSTALLATION OF 55 LINEAR FEET OF HEAVY DUTY SIDEWALK SHED FOR REMEDIAL REPAIRS. SIDEWALK SHED SHALL COMPLY WITH LL 33/91. NO CHANGE IN USE,
2006-04-06Permit EQ — ISSUED
2005
2005-11-17DOB violation E:
2005-11-17DOB violation E:
2005-11-17DOB violation E:
2005-08-15DOB violation E:
2005-08-15DOB violation E:
2004
2004-11-19DOB violation LL1081:
2004-11-09Permit EW — ISSUED
2004-11-09Permit EW — ISSUED
2004-11-08Permit EW — ISSUED
2004-11-08Permit EW — ISSUED
2004-10-29Job filed: FILING FOR MODIFICATIONS TO EXISTING FIRE ALALRM NEW SMOKE DETECTORS STROBES HORNS AND RELATED DEVICES AS SHO WN ON DRAWINGS FILED HEREWITH NO CHANGE $10,000
2004-10-29Job filed: Filing for HVAC work related to an office alteration as shown on drawings filed herewith. No change in use, egress or occupancy.$45,000
2004-10-29Job filed: Filing for the installation of a storage room as shown on drawings filed herewith. No change in use, egress or occupancy.$70,000
2004-10-29Job filed: Filing for partition changes, floor, new ceiling and miscellaneous general construction work for adn office renovation as shown on drawings filed here$60,000
2004-10-29Job filed: Filing for mechanical work related to the storage room as shown on drawings filed herewith. No change in use, egress or occupancy.$30,000
2004-10-29Job filed: FILING FOR MODIFICATIONS TO EXISTING FIRE ALALRM NEW SMOKE DETECTORS STROBES HORNS AND RELATED DEVICES AS SHO WN ON DRAWINGS FILED HEREWITH NO CHANGE $10,000
2004-10-29Job filed: FILING FOR MODIFICATIONS TO THE EXISTING FIRE ALARM SYSTEM NEW SMOKE DE ECTORS STROBES HORN AND RELATED DEVICES AS SHOWN ON DRAWINGS FILED HEREWITH N$25,000
2004-10-29Job filed: Filing for HVAC work related to an office alteration as shown on drawings filed herewith. No change in use, egress or occupancy.$45,000
2004-10-07ECB Non-Hazardous violation: 83X10 83) RETURN TO SERVICE SO A COMPLETE INSPECTION CAN BE MADE BY THIS DEPARTMENT.$2,500
2004-10-07ECB Non-Hazardous violation: 83X10 83) RETURN TO SERVICE SO A COMPLETE INSPECTION CAN BE MADE BY THIS DEPARTMENT.$2,500
2004-10-05DOB violation E:
2004-10-05DOB violation E:
2004-07-27DOB complaint, category ?
2004-07-27DOB complaint, category ?
2004-07-27ECB Non-Hazardous violation: WORK WITHOUT A PERMIT-WORK NOTED:ERECTED PARTITIONS-ENCLOSING ESCALATOR AT TOP AND BOTTOM OF 5TH AND 6TH FLOOR WITH HVAC UNITS INS
2004-03-30DOB complaint, category ?
2003
2003-08-28Permit EW — ISSUED
2003-08-28Permit EW — ISSUED
2003-08-14Job filed: Filing for the installation of smoke and fire dampers and miscellaneous mechanical work for compliance with LL5 of 1973 as per plans. No change in use$250,000
2003-08-14Job filed: Filing for miscellaneous general construction work for compliance with LL5 of 1973 as per palns. No change in use, egress or occupancy.$250,000
2003-04-03Permit EQ — ISSUED
2003-01-28Permit EW — ISSUED
2002
2002-12-17Permit PL — ISSUED
2002-10-23Permit EW — ISSUED
2002-10-09Job filed: Filing for facade restoration as per plans. No change in use, egress or occupancy.$500,000
2002-09-26DOB violation E: 1P6495
2002-09-26DOB violation E: 1P4636
2002-09-26DOB violation E: 1P6495
2002-09-12Permit EQ — ISSUED
2002-09-06Job filed: INSTALLATION OF HEAVY DUTY SIDEWALK BRIDGE, 240 DURING FACADE REPAIR. NO CHANGE IN EGRESS, USE, OR OCCUPANCY. SHED TO COMPLY WITH LL 33/91. NO MATERIA
2002-09-06Job filed: INSTALLATION OF HEAVY DUTY SIDEWALK BRIDGE, 240 DURING FACADE REPAIR. NO CHANGE IN EGRESS, USE, OR OCCUPANCY. SHED TO COMPLY WITH LL 33/91. NO MATERIA
2002-07-24ECB Non-Hazardous violation: 74X07/ 73X RESTORE TO SERVICE OR FILE FOR REMOVER$2,500
2002-07-24ECB Non-Hazardous violation: 73X07/ 73X RESTORE TO SERVICE PR FILE FOR REMOVAL$2,500
2002-07-09Permit EW — ISSUED
2002-07-09Permit EW — ISSUED
2002-06-27Job filed: Partition modification as per plans filed herewith. No change in use egress or occupancy. This floor complies with LL#5 by means of compartmentation$500,000
2002-06-27Job filed: Mechanical and plumbing modifications on the 5th floor. No change in use egress or occupancy.$300,000
2002-06-26Job filed: Fire Alarm modification on fifth floor as per plans filed herewith. No change in use egress or occupancy.$10,000
2002-01-04Permit EW — ISSUED
2002-01-04Permit EW — ISSUED
2001
2001-12-18Permit EW — ISSUED
2001-12-18Permit EW — ISSUED
2001-12-11Job filed: Modifications to existing Class E fire alarm devices as per plans filed herwith. No change in use, egress, or occupancy.$20,000
2001-11-29Job filed: General construction inclusive of modifications to interior partitions as per plans filed herewith. No change in use, egress, or occupancy.$240,000
2001-11-29Job filed: Mechanical modifications on part of 4th floor as per plans filed herewith. No change in use, egress, or occupancy.$525,000
2001-11-28DOB violation E:
2001-11-28DOB violation E:
2001-08-23Permit EW — ISSUED
2001-08-23Permit EW — ISSUED
2001-08-13Job filed: Filing for the installation of new A/C Units and Related Ductwork as per plans. No change in use, egress or occupancy.$725,000
2001-08-13Job filed: Filing for partition changes, new hung ceiling, raised flooring, doors, windows, louvers, and miscellaneous general construction work as per plans. No$400,000
2001-08-13Job filed: Filing for partition changes, new hung ceiling, raised flooring, doors, windows, louvers, and miscellaneous general construction work as per plans. No$400,000
2001-08-13Job filed: Filing for modifications to the existing fire alarms systems. New & Relocated smoke detectors, speaker strobes, warden stations, shutdown auxilary$100,000
2001-08-13Job filed: Filing for the installation of new A/C Units and Related Ductwork as per plans. No change in use, egress or occupancy.$725,000
2001-07-17Permit EW — ISSUED
2001-05-17Permit EW — ISSUED
2001-05-14Job filed: FILING HEREWITH FOR MECHANICAL WORK AS PER PLANS NO CHANGE IN USE EGRESS OR OCCUPANCY$35,000
2001-05-14Job filed: FILING HEREWITH FOR MECHANICAL WORK AS PER PLANS NO CHANGE IN USE EGRESS OR OCCUPANCY$35,000
2001-03-14Job filed: FILING FOR PARTITION CHANGES, NEW FLOORI NG AND MISCELLAMEOUS GENERAL CO STRUCTION WORK AS PER PLANS NO CHANGE IN USE EGRESS OR OCCUPQNCY$350,000
2001-03-14Job filed: FILING FOR PARTITION CHANGES, NEW FLOORI NG AND MISCELLAMEOUS GENERAL CO STRUCTION WORK AS PER PLANS NO CHANGE IN USE EGRESS OR OCCUPQNCY$350,000
2001-03-07Job filed: FILING FOR MINOR PARTITION CHANGES, NEW HUNG CEILING, FLOORING AND MISCE LLANEOUS GENERAL CONSTRUCTION WORK AS PER PLANS. NO CHANGE IN USE, EGRESS OR $250,000
2001-03-07Job filed: FILING FOR THE UPGRADE OF EXISTING MECHA NICAL UNITS AND MODIFICATIONS T RELATED DUCTWORK AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$400,000
2001-03-07Job filed: FILING FOR THE UPGRADE OF EXISTING MECHA NICAL UNITS AND MODIFICATIONS T RELATED DUCTWORK AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.$400,000
2001-03-07Job filed: FILING FOR MINOR PARTITION CHANGES, NEW HUNG CEILING, FLOORING AND MISCE LLANEOUS GENERAL CONSTRUCTION WORK AS PER PLANS. NO CHANGE IN USE, EGRESS OR $250,000
2000
2000-12-29Permit EW — ISSUED
2000-12-29Permit EW — ISSUED
2000-12-21Job filed: Filing for the removal of non-load bearing partitions, hung ceiling, flooring an d two security safes as per plans. No change in use, egress or occup$30,000
2000-12-21Job filed: Filing for the removal of non-load bearing partitions, hung ceiling, flooring an d two security safes as per plans. No change in use, egress or occup$30,000
2000-11-14Job filed: Filing for modifications to existing HVAC system as per plans. No change in use, egress or occupancy.$200,000
2000-11-06ECB Non-Hazardous violation: 73A05 (73)DEVICE NO 1E305 HAS BEEN REMOVED WITHOUT ANY PROPER FILING.
2000-11-06ECB Non-Hazardous violation: 73A05 (73)DEVICE NO:1E472 HAS BEEN REMOVED WITHOUT PROPER FILING.
2000-10-04DOB violation E: 1P4636
2000-10-04DOB violation E: 1P4637
2000-10-04DOB violation E: 1P6495
2000-10-04DOB violation E: 1E303
2000-10-04DOB violation E: 1P6493
2000-10-04DOB violation E: 1E304
2000-01-13Permit EW — ISSUED
2000-01-13Permit EW — ISSUED
2000-01-13Permit EW — ISSUED
2000-01-13Permit EW — ISSUED
1999
1999-10-14ECB Non-Hazardous violation: 73X,RETURN TO SERVICE$2,500
1999-10-14ECB Non-Hazardous violation: 73X,RETURN TO SERVICE.$2,500
1999-09-02Permit EW — ISSUED
1999-09-02Permit EW — ISSUED
1999-09-02Permit EW — ISSUED
1999-09-02Permit EW — ISSUED
1999-05-17Permit EW — ISSUED
1999-05-17Permit EW — ISSUED
1999-03-09Permit EW — ISSUED
1999-03-09Permit EW — ISSUED
1998
1998-11-27Permit EW — ISSUED
1998-11-27Permit EW — ISSUED
1998-11-16Permit EW — ISSUED
1998-11-16Permit EW — ISSUED
1998-10-07Permit EW — ISSUED
1998-10-07Permit EW — ISSUED
1998-07-23ECB Non-Hazardous violation: 73X07,. -73-RETURN DEVICE TO SERVICE FOR PROPER INSPECTION.$2,500
1998-07-23ECB Non-Hazardous violation: 73X07,. 73 RETURN DEVICE TO SERVICE FOR PROPER INSPECTION.$2,500
1998-07-23ECB Non-Hazardous violation: 73X07,. 73-RETURN DEVICE TO SERVICE FOR PROPER INSPECTION.$2,500
1998-07-23ECB Non-Hazardous violation: 73X07,. 73- RETURN DEVICE TO SERVICE FOR PROPER INSPECTION.$2,500
1998-06-01ECB Non-Hazardous violation: 73X 73-PUT ESCALATOR BE IN SERVICE IN FILE PAPER FOR REMOVED.$2,500
1998-06-01ECB Non-Hazardous violation: 50H50O37A44O 37-CONTACT BLOCK OUT SU-GH-HR-TLR.$2,500
1998-06-01ECB Non-Hazardous violation: 44O50O50H2X 50-LOW BRUSH ON MAIN MACHINE.$2,500
1998-06-01ECB Non-Hazardous violation: 73X50H50O37A2X 73-PUT ELEVATOR BACK IN SERVICE TO BE INSPECTED BY D.O.B. INSPECTOR 50-LOW BRUSH ON MAIN MACHINE 37-CONTACT BLOCK O$2,500
1998-06-01ECB Non-Hazardous violation: 50H50O37A44O 50-LOW BRUSH ON MAIN MACHINE 37-CONTACT BLOCK OUT LS-AB-XCX-SE-HR-SU-LX-DGD-DGD-MLY-CX-DDUD-LTZ$2,500
1998-06-01ECB Non-Hazardous violation: 37A73O 37-CONTACT BLOCK OUT HG-EX$2,500
1998-06-01ECB Non-Hazardous violation: 73X 73-PUT ELEVATOR BE IN SECURE OR FILE PAPER FOR REMOVED.$2,500
1998-06-01ECB Non-Hazardous violation: 73U37A50O73O10I 38-PUT THE RIGHTY CITY I.D. NUMBER ON THE DEVICE 1P6493 37-CONTACT BLOC OUT 1AE-ATD-EX-ERT-GLX-10-7TH FL PUSH BUTT$2,500
1998-06-01ECB Non-Hazardous violation: 73X 73-PUT ESCALATOR BACK IN SERVICE TO BE INSPECTED BY D.O.B. OR FILE OR REMOVED.$2,500
1998-06-01ECB Non-Hazardous violation: 73X 73-PUT ESCALATOR BE IN SERVICE OR FILE PAPER FOR REMOVED.$2,500
1997
1997-09-26Permit EW — ISSUED
1997-09-26Permit EW — ISSUED
1997-09-26Permit EW — ISSUED
1997-07-24Permit PL — ISSUED
1997-03-11Permit EW — ISSUED
1997-03-11Permit EW — ISSUED
1996
1996-12-16Permit EW — ISSUED
1996-12-16Permit EW — ISSUED
1995
1995-06-28Permit EW — ISSUED
1995-05-09Permit EW — ISSUED
1995-05-09Permit EW — ISSUED
1995-02-02Permit EW — ISSUED
1994
1994-09-02Permit EW — ISSUED
1994-06-03Permit EW — ISSUED
1994-06-03Permit EW — ISSUED
1994-05-12Permit EW — ISSUED
1994-04-13Permit EW — ISSUED
1993
1993-07-07Permit PL — ISSUED
1993-07-07Permit EW — ISSUED
1993-05-20Permit EW — ISSUED
1991
1991-07-11Permit EW — ISSUED
1991-07-11Permit EW — ISSUED
1990
1990-07-30Permit EW — ISSUED
1990-07-30Permit EW — ISSUED
1989
1989-03-31DOB violation LL5:
1988
1988-11-17DOB violation E: (51) PROPERLY TAG GOVERNOR TO SHOW FIVE(5) YEAR SAFTEY TEST
1988-11-17DOB violation E: (51) PROPERLY TAG GOVERNOR TO SHOW FIVE (5) YEAR TEST
1988-11-17DOB violation E: (51) PROPERLY TAG GOVERNOR TO SHOW FIVE (5) YEAR SAFTEY TEST
1988-11-17DOB violation E: (51) RESTORE TO COMPLETE SERVICE SO A FULL INSPECTION CAN BE COMP LETED BY THIS DEPARTMENT. (52) PROPERLY TAG GOVERNOR FOR FIV
1988-11-17DOB violation E: (51) PROPERLY TAG GOVERNOR TO SHOW FIVE (5) YEAR SAFTEY TEST
1988-11-17DOB violation E: (51) PROPERLY TAG GOVERNOR TO SHOW FIVE (5) YEAR SAFTEY TEST